630 1/4-3/4 E 42ND ST 90011

Certificate Information: 630 1/4-3/4 E 42ND ST 90011

Application / Permit
21016-20000-06814
Plan Check / Job No.
B21VN03185
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT (E ) IRR SHAPED 27'-8" X 25'-5" GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) BELOW (E) DUPLEX ALL WORK PER ENG
Permit Issued
Issued on 10/1/2021
Issuing Office
Current Status
CofO Issued on 6/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 4/29/2021 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 5/4/2021 OMID HEDAYAT
Applicant returned to address corrections 8/11/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 8/31/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 9/21/2021 SEWADA ZADOORAN MILAGARDI
No Progress 9/21/2021 SEWADA ZADOORAN MILAGARDI
Plan Check Approved 9/21/2021 SEWADA ZADOORAN MILAGARDI
Issued 10/1/2021 APPLICANT
CofO in Progress 6/20/2023 BRENDAN MORELLI
Permit Finaled 6/25/2023 DEROLD HAUFF
CofO Issued 6/25/2023 DEROLD HAUFF
Permit Finaled 6/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/1/2021 WALLIE JONG
Sewer availability Cleared 6/1/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/2/2021 WALLIE JONG
Historic Resource Verification Cleared 6/7/2021 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 6/18/2021 DAVID URITA
ZI Cleared 6/18/2021 DAVID URITA
Hydrant and Access approval Cleared 7/20/2021 MATTHEW CRAIG
Construction near power lines Cleared 7/30/2021 RIDWAN HARDY
Construction within easement Cleared 7/30/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/22/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 2/22/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 2/22/2022 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 2/22/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 4/15/2022 Approved HORACE FULTZ
PLUMBING-Rough 4/15/2022 Corrections Issued HORACE FULTZ
Wood Frame 4/15/2022 Corrections Issued HORACE FULTZ
BUILDING-Rough-Frame 5/10/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 5/10/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 5/10/2022 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 1/19/2023 Approved BRENDAN MORELLI
Footing/Foundation/Slab 1/19/2023 Approved BRENDAN MORELLI
HVAC-Rough 1/19/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 1/19/2023 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 1/27/2023 Approved BRENDAN MORELLI
Green Building Rough 1/27/2023 Approved BRENDAN MORELLI
HVAC-Rough 1/27/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 1/27/2023 Approved BRENDAN MORELLI
Deputy Other (see comments) 2/3/2023 Conditional Approval BRENDAN MORELLI
Insulation 2/28/2023 Approved BRENDAN MORELLI
Shower Pan 3/2/2023 Approved BRENDAN MORELLI
Drywall Nailing 3/13/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 3/13/2023 Partial Approval BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 5/17/2023 SGSOV Not Ready RICHARD DOCKUS
ELECTRICAL-Final 6/8/2023 Conditional Approval BRENDAN MORELLI
Final 6/8/2023 Not Ready for Inspection BRENDAN MORELLI
Green Building Final 6/8/2023 Not Ready for Inspection BRENDAN MORELLI
HVAC-Final 6/8/2023 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 6/8/2023 Corrections Issued BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 6/8/2023 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 6/8/2023 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 6/15/2023 Approved BRENDAN MORELLI
Final 6/15/2023 OK to Issue CofO BRENDAN MORELLI
Green Building Final 6/15/2023 Approved BRENDAN MORELLI
HVAC-Final 6/15/2023 Approved BRENDAN MORELLI
PLUMBING-Final 6/15/2023 Approved BRENDAN MORELLI
Smoke Detectors 6/15/2023 Approved BRENDAN MORELLI