23055 W CALIFA ST 91367
Certificate Information: 23055 W CALIFA ST 91367
- Application / Permit
- 21016-20000-06750
- Plan Check / Job No.
- B21VN03155
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTEROR REMODEL (E) SFD AND RAISE THE ROOF IN LIVING/DINNING ROOM AND ADDITION TO FRONT PORCH ENTRANCE
- Permit Issued
- Issued on 6/18/2022
- Issuing Office
- Current Status
- Issued on 6/18/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 4/27/2021 | MOHAMMAD ESMAILI |
| Quality Review Completed | 5/6/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/1/2021 | APPLICANT |
| Applicant returned to address corrections | 6/5/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 6/16/2022 | MOHAMMAD ESMAILI |
| Issued | 6/18/2022 | APPLICANT |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 10/25/2021 | DANG NGUYEN |
| Low Impact Development | Cleared | 2/3/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 5/2/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 5/17/2022 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 5/17/2022 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 5/17/2022 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 6/16/2022 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rahbar,, Farzin S; Lic. No.: S2833 | 20812 VENTURA BLVD 200 WOODLAND HILLS, CA 91364 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/22/2022 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 10/5/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 10/18/2022 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2023 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 5/19/2023 | Approved | TROY SANDERS |
| HVAC-Rough | 5/19/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 5/19/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 5/23/2023 | Partial Approval | TROY SANDERS |
| Insulation | 6/9/2023 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 6/9/2023 | Partial Approval | HORACE FULTZ |
| Drywall Nailing | 6/20/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 6/20/2023 | Partial Approval | TROY SANDERS |
| Shower Pan | 9/21/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 9/29/2023 | Approved | MORRIS JACKSON |
| Gas Test | 3/22/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 6/18/2024 | Approved | GEVORK IPCHYAN |
| Final | 6/18/2024 | Partial Approval | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/18/2024 | SGSOV Approved | GEVORK IPCHYAN |
| Smoke Detectors | 6/18/2024 | Approved | GEVORK IPCHYAN |
| Final | 10/4/2024 | Partial Approval | TROY SANDERS |