11233 N MCLENNAN AVE 91344

Certificate Information: 11233 N MCLENNAN AVE 91344

Application / Permit
21016-20000-06717
Plan Check / Job No.
B21VN03129
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT GER GCS 65852.2(e)(1)(A). ALL WORK SHALL CONFORM TO THE WFPP.
Permit Issued
Issued on 5/11/2021
Issuing Office
Current Status
CofO Corrected on 11/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 COLIN LOREDO
Corrections Issued 3/20/2021 COLIN LOREDO
Building Plans Picked Up 3/26/2021 APPLICANT
Plan Check Approved 4/26/2021 COLIN LOREDO
Issued 5/11/2021 APPLICANT
CofO in Progress 10/29/2021 DAVID SCANTLIN
CofO Issued-Status Void 10/29/2021 JOHN JANSON
Permit Finaled-Status Void 10/29/2021 JOHN JANSON
Re-Activate Permit 11/1/2021 JOHN JANSON
Permit Finaled 11/1/2021 JOHN JANSON
CofO Corrected 11/1/2021 JOHN JANSON
Permit Finaled 11/1/2021 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/31/2021 MARKOS PEREZ-BRAN
Address approval Cleared 4/7/2021 GABRIEL ROBLES
Sewer availability Cleared 4/7/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/14/2021 Approved DAVID SCANTLIN
Deputy Drilled-In Anchors 6/30/2021 Approved SHAVONNE ESPINOZA
Footing/Foundation/Slab 7/2/2021 Approved DAVID SCANTLIN
Sewer 7/2/2021 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 8/2/2021 Approved DAVID SCANTLIN
ELECTRICAL-Rough 8/2/2021 Approved DAVID SCANTLIN
Green Building Rough 8/2/2021 Approved DAVID SCANTLIN
PLUMBING-Rough 8/2/2021 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 8/2/2021 Approved DAVID SCANTLIN
Wood Frame 8/2/2021 Approved DAVID SCANTLIN
Insulation 8/6/2021 Partial Approval DEANDRE HOFFMAN
Insulation 8/10/2021 Approved DAVID SCANTLIN
Interior/Exterior Lathing 8/10/2021 Partial Approval DAVID SCANTLIN
Drywall Nailing 8/13/2021 Approved DEANDRE HOFFMAN
Final 10/5/2021 Corrections Issued DAVID SCANTLIN
Green Building Final 10/5/2021 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 10/5/2021 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 10/5/2021 Approved DAVID SCANTLIN
Final 10/28/2021 OK to Issue CofO DAVID SCANTLIN
Green Building Final 10/28/2021 Approved DAVID SCANTLIN