1736 S VICTORIA AVE 90019

Certificate Information: 1736 S VICTORIA AVE 90019

Application / Permit
21016-20000-06702
Plan Check / Job No.
B21VN03115
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A); AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
Permit Issued
Issued on 8/12/2021
Issuing Office
Current Status
CofO Issued on 1/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 SEAN SHAHMIRI
Corrections Issued 3/28/2021 SEAN SHAHMIRI
Applicant returned to address corrections 7/21/2021 SEAN SHAHMIRI
Applicant returned to address corrections 8/4/2021 SEAN SHAHMIRI
Plan Check Approved 8/4/2021 SEAN SHAHMIRI
Issued 8/12/2021 APPLICANT
CofO in Progress 12/30/2022 STUART CHAPMAN
Permit Finaled 1/3/2023 DEROLD HAUFF
CofO Issued 1/3/2023 DEROLD HAUFF
Permit Finaled 1/3/2023 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 4/8/2021 AMANDA KAINER
Miscellaneous Cleared 4/8/2021 AMANDA KAINER
Miscellaneous Cleared 4/8/2021 AMANDA KAINER
Address approval Cleared 4/9/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 4/9/2021 ROSA SILVA
Sewer availability Cleared 4/9/2021 ROSA SILVA
Construction near power lines Cleared 6/12/2021 RIDWAN HARDY

Contact Information

Contractor True Vision Development Inc; Lic. No.: 1047713-B 1332 W PARADE STREET      LONG BEACH, CA 90810
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/20/2021 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 8/24/2021 Approved STUART CHAPMAN
Footing/Foundation/Slab 9/17/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 9/30/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Approved STUART CHAPMAN
HVAC-Rough 9/30/2021 Approved STUART CHAPMAN
PLUMBING-Rough 9/30/2021 Approved STUART CHAPMAN
Sewer 11/15/2021 Approved JUSTIN HAWLEY
Insulation 1/5/2022 Partial Approval STUART CHAPMAN
Drywall Nailing 1/13/2022 Conditional Approval CHRIS CHRISTENSEN
Green Building Rough 1/13/2022 Conditional Approval CHRIS CHRISTENSEN
Sewer 7/21/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/17/2022 Approved STUART CHAPMAN
Drywall Nailing 10/17/2022 Approved STUART CHAPMAN
Final 10/17/2022 Corrections Issued STUART CHAPMAN
Green Building Final 10/17/2022 Approved STUART CHAPMAN
Green Building Rough 10/17/2022 Approved STUART CHAPMAN
METHANE-Final 10/17/2022 Approved STUART CHAPMAN
METHANE-Rough 10/17/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/17/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 10/17/2022 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 10/25/2022 Not Ready for Inspection STUART CHAPMAN
Final 10/25/2022 Corrections Issued STUART CHAPMAN
HVAC-Final 10/25/2022 Approved STUART CHAPMAN
PLUMBING-Final 10/25/2022 Approved STUART CHAPMAN
Smoke Detectors 10/25/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 10/28/2022 Approved STUART CHAPMAN
Final 10/28/2022 Partial Approval STUART CHAPMAN
Final 12/7/2022 Corrections Issued STUART CHAPMAN
Final 12/30/2022 OK to Issue CofO STUART CHAPMAN
Service/Power Release 12/30/2022 Approved STUART CHAPMAN