7147 W MACAPA DR 90068

Certificate Information: 7147 W MACAPA DR 90068

Application / Permit
21016-20000-06701
Plan Check / Job No.
B21VN03114
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL (E) SINGLE FAMILY DWELLING TO ADD 2 MORE BEDROOM , NEW SHINGLE ROOF & WINDOWS. NO ADDITIONAL SF AREA TO THE BUILDING. ALL WORK PER ENGINEER.
Permit Issued
Issued on 6/16/2021
Issuing Office
Current Status
Permit Finaled on 3/1/2023

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 PARISA ZAHABI
Building Plans Picked Up 3/19/2021 APPLICANT
Corrections Issued 3/20/2021 PARISA ZAHABI
Quality Review Completed 3/22/2021 OMID HEDAYAT
Applicant returned to address corrections 4/12/2021 PARISA ZAHABI
Applicant returned to address corrections 4/23/2021 PARISA ZAHABI
Applicant returned to address corrections 5/4/2021 PARISA ZAHABI
Plan Check Approved 6/16/2021 PARISA ZAHABI
Issued 6/16/2021 APPLICANT
Permit Finaled 3/1/2023 RAUL BARAJAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/23/2021 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 3/23/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 3/23/2021 GUILLERMO PETRA
Sewer availability Cleared 4/14/2021 GUILLERMO PETRA
Grading Pre-Inspection Cleared 4/23/2021 PARISA ZAHABI
Roof/Waste drainage to street Cleared 4/26/2021 GUILLERMO PETRA
Miscellaneous Cleared 6/9/2021 LIZZI BEDUYA
Specific Plan Cleared 6/9/2021 LIZZI BEDUYA

Contact Information

Contractor Owner-Builder       ,
Engineer Peck,, Christopher Mount; Lic. No.: C58162 25 SOUTH EL MOLINO AVE      PASADENA, CA 911012023

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/15/2021 Partial Approval BRIAN SULLIVAN
Underground Mechanical 9/15/2021 Approved BRIAN SULLIVAN
Deputy Drilled-In Anchors 10/1/2021 Conditional Approval BRIAN SULLIVAN
ELECTRICAL-Rough 10/4/2021 Partial Approval BRIAN SULLIVAN
Footing/Foundation/Slab 10/4/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 10/4/2021 Partial Approval BRIAN SULLIVAN
Underground Mechanical 10/4/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 3/4/2022 Approved BRIAN SULLIVAN
Gas Test 3/4/2022 Approved BRIAN SULLIVAN
Grounding or Bonding 3/4/2022 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 3/4/2022 Approved BRIAN SULLIVAN
Shower Pan 3/4/2022 Approved BRIAN SULLIVAN
Deputy Wood Construction 4/19/2022 Conditional Approval BRIAN SULLIVAN
HVAC-Rough 5/16/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 7/19/2022 Approved BRIAN SULLIVAN
Insulation 7/19/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 7/19/2022 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 7/26/2022 Approved BRIAN SULLIVAN
Drywall Nailing 9/6/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 3/1/2023 Approved RAUL BARAJAS
Final 3/1/2023 Permit Finaled RAUL BARAJAS
HVAC-Final 3/1/2023 Approved RAUL BARAJAS
PLUMBING-Final 3/1/2023 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/1/2023 SGSOV Approved RAUL BARAJAS
Smoke Detectors 3/1/2023 Approved RAUL BARAJAS