3840 S SOMERSET DR 90008
Certificate Information: 3840 S SOMERSET DR 90008
- Application / Permit
- 21016-20000-06680
- Plan Check / Job No.
- B21VN03091
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL OF (E) ONE STORY SINGLE FAMILY DWELLING; ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 5/18/2021
- Issuing Office
- Current Status
- Permit Finaled on 11/21/2022
Permit Application Status History
| Submitted | 3/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | SEAN SHAHMIRI |
| Corrections Issued | 3/20/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 3/24/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/18/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 5/18/2021 | SEAN SHAHMIRI |
| Issued | 5/18/2021 | APPLICANT |
| Permit Finaled | 11/17/2022 | ANTHONY EGSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/8/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 9/8/2021 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 9/13/2021 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 10/6/2021 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 12/7/2021 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 12/7/2021 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 12/7/2021 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 12/29/2021 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 12/29/2021 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 12/29/2021 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 1/19/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 1/19/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/21/2022 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 1/21/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/31/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 1/31/2022 | Conditional Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 2/8/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 3/10/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 3/14/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 4/26/2022 | Approved | ANTHONY EGSON |
| Insulation | 5/4/2022 | Approved | ANTHONY EGSON |
| Sewer | 5/4/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 5/12/2022 | No Access for Inspection | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2022 | No Access for Inspection | HORACE FULTZ |
| Green Building Rough | 5/12/2022 | No Access for Inspection | HORACE FULTZ |
| Shower Pan | 5/12/2022 | No Access for Inspection | HORACE FULTZ |
| Shower Pan | 5/16/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 5/27/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/27/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 5/27/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/3/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/30/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/7/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 11/7/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 11/7/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 11/7/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 11/7/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 11/7/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/7/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 11/7/2022 | Approved | ANTHONY EGSON |
| Final | 11/17/2022 | Permit Finaled | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Approved | ANTHONY EGSON |