884 E WARREN AVE 90291

Certificate Information: 884 E WARREN AVE 90291

Application / Permit
21016-20000-06591
Plan Check / Job No.
B21VN03058
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). WORK PER ENGINEER.
Permit Issued
Issued on 10/5/2021
Issuing Office
Current Status
CofO Issued on 6/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 RICHARD GARCIA
Corrections Issued 3/28/2021 RICHARD GARCIA
Plan Check Approved 9/13/2021 ROSENDO MEDINA
Issued 10/5/2021 APPLICANT
CofO in Progress 6/27/2022 JESUS RODRIGUEZ
Permit Finaled 6/30/2022 DANIEL ORRANTE
CofO Issued 6/30/2022 DANIEL ORRANTE
Permit Finaled 6/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 5/10/2021 PEDRO AYALA
Address approval Cleared 5/12/2021 ANTHONY MAINEZ
Sewer availability Cleared 5/12/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 5/13/2021 ANTHONY MAINEZ
Hydrant and Access approval Cleared 8/20/2021 GILBERT URREA

Contact Information

Contractor Gaga Builders Inc; Lic. No.: 1038675-B 22287 MULHOLLAND HWY UNIT #194      CALABASAS, CA 91302
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/14/2021 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 10/18/2021 Approved DAVID FEILER
Underground Mechanical 10/18/2021 Partial Approval DAVID FEILER
Underground Mechanical 10/22/2021 Approved RYAN SALAZAR
BUILDING-Rough-Frame 11/22/2021 Partial Approval DAVID FEILER
ELECTRICAL-Rough 11/22/2021 Approved DAVID FEILER
HVAC-Rough 11/22/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 11/22/2021 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 12/1/2021 Approved RICHARD STEINBACH
Green Building Rough 12/1/2021 Approved RICHARD STEINBACH
HVAC-Rough 12/1/2021 Approved RICHARD STEINBACH
PLUMBING-Rough 12/1/2021 Approved RICHARD STEINBACH
Insulation 12/6/2021 Approved JOHN KAYON
Drywall Nailing 12/16/2021 Approved JOHN KAYON
Shower Pan 12/16/2021 Approved JOHN KAYON
Interior/Exterior Lathing 12/21/2021 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 1/3/2022 Not Ready for Inspection EVAN COOPER
Pre-Inspection 1/3/2022 Approved EVAN COOPER
Interior/Exterior Lathing 1/18/2022 Approved JOHN KAYON
ELECTRICAL-Final 6/16/2022 Approved BOBBY KEY
Final 6/16/2022 Corrections Issued BOBBY KEY
Green Building Final 6/16/2022 Approved BOBBY KEY
HVAC-Final 6/16/2022 Approved BOBBY KEY
PLUMBING-Final 6/16/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 6/16/2022 SGSOV Not Ready BOBBY KEY
Smoke Detectors 6/16/2022 Approved BOBBY KEY
Final 6/21/2022 Conditional Approval JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/21/2022 SGSOV Approved JESUS RODRIGUEZ