4824 N MARY ELLEN AVE 91423
Certificate Information: 4824 N MARY ELLEN AVE 91423
- Application / Permit
- 21016-20000-06586
- Plan Check / Job No.
- B21VN03054
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ECPC: INTERIOR REMODEL TO THE (E) SFD.
- Permit Issued
- Issued on 6/21/2021
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 1/27/2022
Permit Application Status History
| Submitted | 3/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/24/2021 | JESSE ARELLANO |
| Corrections Issued | 3/24/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 5/19/2021 | JESSE ARELLANO |
| Plan Check Approved | 6/2/2021 | JESSE ARELLANO |
| Building Plans Picked Up | 6/7/2021 | APPLICANT |
| Issued | 6/21/2021 | APPLICANT |
| Permit Finaled | 1/27/2022 | JACK KARGODORIAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/20/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/29/2021 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 6/30/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 8/23/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 8/23/2021 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 8/23/2021 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 8/23/2021 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/23/2021 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 9/2/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/2/2021 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 9/2/2021 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/8/2021 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Shower Pan | 9/8/2021 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Drywall Nailing | 9/9/2021 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Shower Pan | 9/9/2021 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Drywall Nailing | 9/10/2021 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 9/10/2021 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 10/5/2021 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 1/27/2022 | Approved | JACK KARGODORIAN |
| Final | 1/27/2022 | Permit Finaled | JACK KARGODORIAN |
| MERV13>=Final | 1/27/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 1/27/2022 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 1/27/2022 | Approved | JACK KARGODORIAN |