13326-13328 W CHASE ST 91331

Certificate Information: 13326-13328 W CHASE ST 91331

Application / Permit
21016-20000-06453
Plan Check / Job No.
B21VN02993
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 23'-3" X 19'-3" ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/1/2021
Issuing Office
Current Status
Issued on 9/1/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/15/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 RICHARD GARCIA
Corrections Issued 3/31/2021 RICHARD GARCIA
Applicant returned to address corrections 5/13/2021 LUISANGEL VALENZUELA
Applicant returned to address corrections 5/20/2021 LUISANGEL VALENZUELA
Plan Check Approved 8/17/2021 LUISANGEL VALENZUELA
Building Plans Picked Up 8/18/2021 APPLICANT
Issued 9/1/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/29/2021 GABRIEL ROBLES
Sewer availability Cleared 4/29/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/18/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Shagirian,, Ashot; Lic. No.: C79415 11337 RUNNYMEDE ST      SUN VALLEY, CA 91352

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/2/2021 Corrections Issued GREGG CUMMINGS
Sewer 12/2/2021 Approved GREGG CUMMINGS
Footing/Foundation/Slab 6/30/2022 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 11/7/2022 Not Ready for Inspection GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 11/10/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 11/10/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 12/16/2022 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 12/16/2022 Corrections Issued GREGG CUMMINGS
Green Building Rough 12/16/2022 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 1/17/2023 Corrections Issued GREGG CUMMINGS
HVAC-Rough 1/17/2023 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 1/17/2023 Corrections Issued GREGG CUMMINGS
Special/Order Compliance 2/9/2023 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 2/13/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 2/13/2023 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 2/13/2023 Corrections Issued GREGG CUMMINGS
Wood Frame 2/13/2023 Corrections Issued GREGG CUMMINGS
HVAC-Rough 3/3/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 3/7/2023 Approved GREGG CUMMINGS
ELECTRICAL-Rough 3/7/2023 Approved GREGG CUMMINGS
Green Building Rough 3/7/2023 Approved GREGG CUMMINGS
PLUMBING-Rough 3/7/2023 Approved GREGG CUMMINGS
Insulation 3/17/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/17/2023 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 4/12/2023 Approved GREGG CUMMINGS
Footing/Foundation/Slab 4/12/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 4/12/2023 Not Ready for Inspection GREGG CUMMINGS
Shower Pan 5/2/2023 Approved GREGG CUMMINGS