8920-8922 N MOORCROFT AVE 91304

Certificate Information: 8920-8922 N MOORCROFT AVE 91304

Application / Permit
21016-20000-06426
Plan Check / Job No.
B21VN02986
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT PORTION OF EX GARAGE INTO ACCESSORY DWELLING UNIT PER ORD #186,481 AND REMAINING PORTION INTO A BATHRM & LAUNDRY RM FOR THE MAIN DWELLING UNIT. SEE COMMENTS.
Permit Issued
Issued on 8/6/2021
Issuing Office
Current Status
CofO Issued on 1/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2021 APPLICANT
Assigned to Plan Check Engineer 3/26/2021 HAYATO TSUCHIYA
Corrections Issued 4/18/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 6/1/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 6/24/2021 HAYATO TSUCHIYA
Building Plans Picked Up 6/24/2021 APPLICANT
Plan Check Approved 8/2/2021 HAYATO TSUCHIYA
Issued 8/6/2021 APPLICANT
CofO in Progress 12/20/2022 CHRIS CHRISTENSEN
Permit Finaled 1/4/2023 JOHN JANSON
CofO Issued 1/4/2023 JOHN JANSON
Permit Finaled 1/4/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/21/2021 ADRIAN CASTRO
Sewer availability Cleared 4/21/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/22/2021 ADRIAN CASTRO
Grading Pre-Inspection Cleared 4/23/2021 BRIAN MILLER

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/12/2021 Partial Approval TROY SANDERS
Footing/Foundation/Slab 10/12/2021 Partial Approval TROY SANDERS
Deputy Drilled-In Anchors 10/14/2021 Approved JESUS PINEDA
Footing/Foundation/Slab 10/18/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 10/26/2021 Corrections Issued DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 10/26/2021 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 10/26/2021 Approved DAVID STEPANYAN
Green Building Rough 10/26/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 10/26/2021 Corrections Issued DAVID STEPANYAN
BUILDING-Rough-Frame 11/1/2021 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 11/1/2021 Partial Approval DAVID STEPANYAN
Interior/Exterior Lathing 11/12/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 1/19/2022 Partial Approval TROY SANDERS
Green Building Rough 1/19/2022 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 1/19/2022 Approved TROY SANDERS
Insulation 1/24/2022 Approved JESUS PINEDA
BUILDING-Rough-Frame 1/26/2022 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/26/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 1/26/2022 Approved JESUS PINEDA
Shower Pan 1/26/2022 Approved JESUS PINEDA
Drywall Nailing 1/27/2022 Not Ready for Inspection JESUS PINEDA
Drywall Nailing 2/1/2022 Approved MORRIS JACKSON
ELECTRICAL-Final 9/22/2022 Approved CHRIS CHRISTENSEN
Final 9/22/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 9/22/2022 Approved CHRIS CHRISTENSEN
HVAC-Final 9/22/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 9/22/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 9/22/2022 Approved CHRIS CHRISTENSEN
Final 12/19/2022 OK to Issue CofO CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Approved CHRIS CHRISTENSEN