374-376 W 12TH ST 90731
Certificate Information: 374-376 W 12TH ST 90731
- Application / Permit
- 21016-20000-06398
- Plan Check / Job No.
- B21VN02964
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- RE-FRAME & INTERIOR REMODEL TO (E) DUPLEX INCLUDING NEW LAYOUT
- Permit Issued
- Issued on 2/15/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 5/8/2025
Permit Application Status History
| Submitted | 3/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | PETER MOSESIAN |
| Corrections Issued | 4/20/2021 | PETER MOSESIAN |
| Quality Review Completed | 4/26/2021 | OMID HEDAYAT |
| Plan Check Approved | 7/18/2023 | PETER MOSESIAN |
| Issued | 2/15/2024 | APPLICANT |
| Permit Finaled | 5/8/2025 | JOSEPH MCGARRY |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/14/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2022 | JOSE HERNANDEZ |
| Coastal Zone | Cleared | 5/11/2022 | MARITZA PRZEKOP |
| Specific Plan | Cleared | 5/11/2022 | MARITZA PRZEKOP |
| HPOZ | Cleared | 1/4/2023 | DAMIAN GATTO |
| Historic Resource Verification | Cleared | 1/4/2023 | DAMIAN GATTO |
| Redevelopment Project Area | Cleared | 4/12/2023 | GRACIELA ACOSTA |
| Roof/Waste drainage to street | Cleared | 4/12/2023 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Posadas,, John Garcia; Lic. No.: C30786 | 2063 PASEO LUCINDA SAN DIMAS, CA 91773 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/22/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/29/2024 | Approved | JAMES CHAVEZ |
| Special/Order Compliance | 2/29/2024 | Corrections Issued | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2024 | Partial Approval | JAMES CHAVEZ |
| ELECTRICAL-Rough | 4/1/2024 | Corrections Issued | ANSON MAGLASANG |
| HVAC-Rough | 4/1/2024 | Corrections Issued | ANSON MAGLASANG |
| PLUMBING-Rough | 4/1/2024 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Final | 4/11/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Rough | 4/11/2024 | No Access for Inspection | JAMES CHAVEZ |
| Special/Order Compliance | 4/15/2024 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 5/10/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 5/10/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/10/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 5/10/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/10/2024 | Approved | EUGENE CASSIDY |
| Insulation | 5/31/2024 | Corrections Issued | ANSON MAGLASANG |
| Insulation | 6/5/2024 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 6/13/2024 | Partial Approval | JAMES CHAVEZ |
| Special/Order Compliance | 6/13/2024 | Corrections Issued | JAMES CHAVEZ |
| Drywall Nailing | 6/20/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/22/2024 | Not Ready for Inspection | ANSON MAGLASANG |
| Final | 11/22/2024 | No Access for Inspection | ANSON MAGLASANG |
| HVAC-Final | 11/22/2024 | No Access for Inspection | ANSON MAGLASANG |
| PLUMBING-Final | 11/22/2024 | No Access for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 11/22/2024 | SGSOV Not Ready | ANSON MAGLASANG |
| Smoke Detectors | 11/22/2024 | No Access for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 11/25/2024 | SGSOV Not Ready | JOSEPH MCGARRY |
| ELECTRICAL-Final | 11/26/2024 | Corrections Issued | JOSEPH MCGARRY |
| Final | 11/26/2024 | Corrections Issued | JOSEPH MCGARRY |
| HVAC-Final | 11/26/2024 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Final | 11/26/2024 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Final | 4/4/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 4/4/2025 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 4/4/2025 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 4/4/2025 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 4/4/2025 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 4/4/2025 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 4/23/2025 | No Access for Inspection | JOSEPH MCGARRY |
| Smoke Detectors | 4/23/2025 | No Access for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 4/29/2025 | Not Ready for Inspection | JOHN KLARIN |
| Final | 4/29/2025 | Not Ready for Inspection | JOHN KLARIN |
| HVAC-Final | 4/29/2025 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Final | 4/29/2025 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 4/29/2025 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Final | 5/8/2025 | Approved | JOSEPH MCGARRY |
| Final | 5/8/2025 | Permit Finaled | JOSEPH MCGARRY |
| HVAC-Final | 5/8/2025 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 5/8/2025 | Approved | JOSEPH MCGARRY |
| Smoke Detectors | 5/8/2025 | Approved | JOSEPH MCGARRY |