374-376 W 12TH ST 90731

Certificate Information: 374-376 W 12TH ST 90731

Application / Permit
21016-20000-06398
Plan Check / Job No.
B21VN02964
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
RE-FRAME & INTERIOR REMODEL TO (E) DUPLEX INCLUDING NEW LAYOUT
Permit Issued
Issued on 2/15/2024
Issuing Office
Metro
Current Status
Permit Finaled on 5/8/2025

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 PETER MOSESIAN
Corrections Issued 4/20/2021 PETER MOSESIAN
Quality Review Completed 4/26/2021 OMID HEDAYAT
Plan Check Approved 7/18/2023 PETER MOSESIAN
Issued 2/15/2024 APPLICANT
Permit Finaled 5/8/2025 JOSEPH MCGARRY

Permit Application Clearance Information

Sewer availability Cleared 4/14/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 5/3/2022 JOSE HERNANDEZ
Coastal Zone Cleared 5/11/2022 MARITZA PRZEKOP
Specific Plan Cleared 5/11/2022 MARITZA PRZEKOP
HPOZ Cleared 1/4/2023 DAMIAN GATTO
Historic Resource Verification Cleared 1/4/2023 DAMIAN GATTO
Redevelopment Project Area Cleared 4/12/2023 GRACIELA ACOSTA
Roof/Waste drainage to street Cleared 4/12/2023 CHRISTOPHER ROCHA

Contact Information

Contractor Owner-Builder       ,
Engineer Posadas,, John Garcia; Lic. No.: C30786 2063 PASEO LUCINDA      SAN DIMAS, CA 91773

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 2/22/2024 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 2/22/2024 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 2/29/2024 Approved JAMES CHAVEZ
Special/Order Compliance 2/29/2024 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 3/13/2024 Partial Approval JAMES CHAVEZ
ELECTRICAL-Rough 4/1/2024 Corrections Issued ANSON MAGLASANG
HVAC-Rough 4/1/2024 Corrections Issued ANSON MAGLASANG
PLUMBING-Rough 4/1/2024 Corrections Issued ANSON MAGLASANG
ELECTRICAL-Final 4/11/2024 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 4/11/2024 No Access for Inspection JAMES CHAVEZ
Special/Order Compliance 4/15/2024 Partial Approval ANSON MAGLASANG
BUILDING-Rough-Frame 5/10/2024 Approved EUGENE CASSIDY
Drywall Nailing 5/10/2024 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 5/10/2024 Approved EUGENE CASSIDY
HVAC-Rough 5/10/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 5/10/2024 Approved EUGENE CASSIDY
Insulation 5/31/2024 Corrections Issued ANSON MAGLASANG
Insulation 6/5/2024 Approved JAMES CHAVEZ
Drywall Nailing 6/13/2024 Partial Approval JAMES CHAVEZ
Special/Order Compliance 6/13/2024 Corrections Issued JAMES CHAVEZ
Drywall Nailing 6/20/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 11/22/2024 Not Ready for Inspection ANSON MAGLASANG
Final 11/22/2024 No Access for Inspection ANSON MAGLASANG
HVAC-Final 11/22/2024 No Access for Inspection ANSON MAGLASANG
PLUMBING-Final 11/22/2024 No Access for Inspection ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 11/22/2024 SGSOV Not Ready ANSON MAGLASANG
Smoke Detectors 11/22/2024 No Access for Inspection ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Not Ready JOSEPH MCGARRY
ELECTRICAL-Final 11/26/2024 Corrections Issued JOSEPH MCGARRY
Final 11/26/2024 Corrections Issued JOSEPH MCGARRY
HVAC-Final 11/26/2024 Corrections Issued JOSEPH MCGARRY
PLUMBING-Final 11/26/2024 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Final 4/4/2025 Corrections Issued BEN MOLSTAD
Final 4/4/2025 Corrections Issued BEN MOLSTAD
HVAC-Final 4/4/2025 Corrections Issued BEN MOLSTAD
PLUMBING-Final 4/4/2025 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Approved BEN MOLSTAD
Smoke Detectors 4/4/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Final 4/23/2025 No Access for Inspection JOSEPH MCGARRY
Smoke Detectors 4/23/2025 No Access for Inspection JOSEPH MCGARRY
ELECTRICAL-Final 4/29/2025 Not Ready for Inspection JOHN KLARIN
Final 4/29/2025 Not Ready for Inspection JOHN KLARIN
HVAC-Final 4/29/2025 Corrections Issued JOHN KLARIN
PLUMBING-Final 4/29/2025 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 4/29/2025 Corrections Issued JOHN KLARIN
ELECTRICAL-Final 5/8/2025 Approved JOSEPH MCGARRY
Final 5/8/2025 Permit Finaled JOSEPH MCGARRY
HVAC-Final 5/8/2025 Approved JOSEPH MCGARRY
PLUMBING-Final 5/8/2025 Approved JOSEPH MCGARRY
Smoke Detectors 5/8/2025 Approved JOSEPH MCGARRY