564 N VIRGIL AVE 90004
Certificate Information: 564 N VIRGIL AVE 90004
- Application / Permit
- 21016-20000-06360
- Plan Check / Job No.
- B21VN02952
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (11) Hotel
- Work Description
- INTERIOR REMODEL TO (E) TWO STORY HOTEL [SEE COMMENTS].
- Permit Issued
- Issued on 2/15/2022
- Issuing Office
- Current Status
- Permit Finaled on 2/6/2023
Permit Application Status History
| Submitted | 3/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | DAWN MC NULTY |
| Corrections Issued | 4/7/2021 | DAWN MC NULTY |
| Quality Review Completed | 4/7/2021 | STEVEN KIM |
| Applicant returned to address corrections | 7/13/2021 | DAWN MC NULTY |
| Plan Check Approved | 2/15/2022 | DAWN MC NULTY |
| Issued | 2/15/2022 | APPLICANT |
| Permit Finaled | 2/6/2023 | EDWIN GREGORYONA |
Permit Application Clearance Information
| CPC | Cleared | 6/7/2021 | PABLO ESTRADA |
| Address approval | Cleared | 6/10/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/10/2021 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 6/28/2021 | BRIAN MILLER |
| Fire Marshal Fire Life Safety | Cleared | 9/20/2021 | MENOA AGHAJANI |
| ZI | Cleared | 9/23/2021 | DANALYNN DOMINGUEZ |
| HPOZ | Cleared | 1/13/2022 | LAMBERT GIESSINGER |
| Tenant Habitability Plan | Cleared | 1/18/2022 | ISMAEL HERNANDEZ |
| DAS Clearance | Cleared | 1/20/2022 | DAWN MC NULTY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/17/2022 | Corrections Issued | SORIN CIRSTOIU |
| Special/Order Compliance | 4/5/2022 | No Access for Inspection | JONATHAN QUACH |
| Special/Order Compliance | 4/12/2022 | Corrections Issued | JONATHAN QUACH |
| Footing/Foundation/Slab | 4/22/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Footing/Foundation/Slab | 10/11/2022 | Partial Inspection | JONATHAN QUACH |
| Deputy Reinf. Concrete | 10/27/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Wood Frame | 11/9/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 11/16/2022 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 11/22/2022 | Partial Approval | JONATHAN QUACH |
| Insulation | 11/23/2022 | Approved | JONATHAN QUACH |
| Drywall Nailing | 11/30/2022 | Partial Approval | RONALD JIMENEZ |
| Pre-Inspection | 12/1/2022 | Corrections Issued | RONALD JIMENEZ |
| Final | 1/6/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 1/6/2023 | SGSOV Not Ready | TIMOTHY POWELL |
| Smoke Detectors | 1/6/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Final | 1/26/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Not Ready | EDWIN GREGORYONA |
| Smoke Detectors | 1/26/2023 | Not Ready for Inspection | RONALD JIMENEZ |
| Final | 1/27/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 1/27/2023 | SGSOV Approved | EDWIN GREGORYONA |
| Smoke Detectors | 1/27/2023 | Approved | EDWIN GREGORYONA |
| Final | 1/31/2023 | Not Ready for Inspection | EDWIN GREGORYONA |
| Final | 2/6/2023 | Permit Finaled | EDWIN GREGORYONA |