564 N VIRGIL AVE 90004

Certificate Information: 564 N VIRGIL AVE 90004

Application / Permit
21016-20000-06360
Plan Check / Job No.
B21VN02952
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
INTERIOR REMODEL TO (E) TWO STORY HOTEL [SEE COMMENTS].
Permit Issued
Issued on 2/15/2022
Issuing Office
Current Status
Permit Finaled on 2/6/2023

Permit Application Status History

Submitted 3/16/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 DAWN MC NULTY
Corrections Issued 4/7/2021 DAWN MC NULTY
Quality Review Completed 4/7/2021 STEVEN KIM
Applicant returned to address corrections 7/13/2021 DAWN MC NULTY
Plan Check Approved 2/15/2022 DAWN MC NULTY
Issued 2/15/2022 APPLICANT
Permit Finaled 2/6/2023 EDWIN GREGORYONA

Permit Application Clearance Information

CPC Cleared 6/7/2021 PABLO ESTRADA
Address approval Cleared 6/10/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 6/10/2021 CECILIO NAVARRO
Sewer availability Cleared 6/10/2021 CECILIO NAVARRO
Grading Pre-Inspection Cleared 6/28/2021 BRIAN MILLER
Fire Marshal Fire Life Safety Cleared 9/20/2021 MENOA AGHAJANI
ZI Cleared 9/23/2021 DANALYNN DOMINGUEZ
HPOZ Cleared 1/13/2022 LAMBERT GIESSINGER
Tenant Habitability Plan Cleared 1/18/2022 ISMAEL HERNANDEZ
DAS Clearance Cleared 1/20/2022 DAWN MC NULTY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/17/2022 Corrections Issued SORIN CIRSTOIU
Special/Order Compliance 4/5/2022 No Access for Inspection JONATHAN QUACH
Special/Order Compliance 4/12/2022 Corrections Issued JONATHAN QUACH
Footing/Foundation/Slab 4/22/2022 Not Ready for Inspection JONATHAN QUACH
Footing/Foundation/Slab 10/11/2022 Partial Inspection JONATHAN QUACH
Deputy Reinf. Concrete 10/27/2022 Conditional Approval MICHAEL ROSENBERG
Wood Frame 11/9/2022 Not Ready for Inspection JONATHAN QUACH
Wood Frame 11/16/2022 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 11/22/2022 Partial Approval JONATHAN QUACH
Insulation 11/23/2022 Approved JONATHAN QUACH
Drywall Nailing 11/30/2022 Partial Approval RONALD JIMENEZ
Pre-Inspection 12/1/2022 Corrections Issued RONALD JIMENEZ
Final 1/6/2023 Not Ready for Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV Not Ready TIMOTHY POWELL
Smoke Detectors 1/6/2023 Not Ready for Inspection TIMOTHY POWELL
Final 1/26/2023 Not Ready for Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 1/26/2023 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 1/26/2023 Not Ready for Inspection RONALD JIMENEZ
Final 1/27/2023 Not Ready for Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 1/27/2023 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 1/27/2023 Approved EDWIN GREGORYONA
Final 1/31/2023 Not Ready for Inspection EDWIN GREGORYONA
Final 2/6/2023 Permit Finaled EDWIN GREGORYONA