2320 N HERCULES DR 90046

Certificate Information: 2320 N HERCULES DR 90046

Application / Permit
21016-20000-06327
Plan Check / Job No.
B21VN02940
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL WITH ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; REDUCE OVERALL SQUUARE FOOTAGE OF BUILDING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/29/2021
Issuing Office
Current Status
CofO Issued on 10/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 SELLA BENYAMIN
Corrections Issued 3/22/2021 SELLA BENYAMIN
Quality Review Completed 3/24/2021 STEVEN KIM
Plan Check Approved 9/28/2021 SELLA BENYAMIN
Issued 9/29/2021 APPLICANT
CofO in Progress 9/18/2024 BRIAN SULLIVAN
CofO Issued 10/28/2024 RUBEN SALAS
Permit Finaled 10/28/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/15/2021 THOMAS LANG
Sewer availability Cleared 4/23/2021 THOMAS LANG
Low Impact Development Cleared 9/2/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/2/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/23/2022 Partial Approval RYAN SALAZAR
Sewer 5/23/2022 Approved RYAN SALAZAR
Footing/Foundation/Slab 6/1/2022 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 6/8/2022 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 5/10/2023 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 5/10/2023 Approved STUART CHAPMAN
PLUMBING-Rough 5/10/2023 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 5/10/2023 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 7/20/2023 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 7/20/2023 Partial Approval STUART CHAPMAN
Shower Pan 7/20/2023 Approved STUART CHAPMAN
HVAC-Rough 7/27/2023 Not Ready for Inspection RAUL BARAJAS
HVAC-Rough 8/1/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/1/2023 Partial Approval STUART CHAPMAN
Insulation 8/9/2023 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 9/8/2023 No Result Entered STUART CHAPMAN
Drywall Nailing 9/8/2023 Corrections Issued STUART CHAPMAN
Insulation 9/8/2023 No Result Entered STUART CHAPMAN
Interior/Exterior Lathing 9/8/2023 Not Ready for Inspection STUART CHAPMAN
Verify Sprinkler Sign Off 9/8/2023 No Result Entered STUART CHAPMAN
Drywall Nailing 9/14/2023 Partial Inspection RAUL BARAJAS
Interior/Exterior Lathing 9/14/2023 Partial Inspection RAUL BARAJAS
Drywall Nailing 9/19/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 9/19/2023 Partial Approval STUART CHAPMAN
Final 7/3/2024 Partial Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 7/3/2024 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 7/3/2024 Partial Inspection RAUL BARAJAS
Final 7/16/2024 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 7/16/2024 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 7/16/2024 Approved RAUL BARAJAS
Final 7/31/2024 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV Not Ready RAUL BARAJAS
Final 8/8/2024 Partial Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 8/8/2024 SGSOV Not Ready BRIAN SULLIVAN
Service/Power Release 8/12/2024 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 8/15/2024 Approved BRIAN SULLIVAN
Final 8/21/2024 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 8/21/2024 SGSOV Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 8/22/2024 Approved BRIAN SULLIVAN
Final 8/22/2024 OK to Issue CofO BRIAN SULLIVAN