15144 W MARTHA ST 91411

Certificate Information: 15144 W MARTHA ST 91411

Application / Permit
21016-20000-06292
Plan Check / Job No.
B21VN02910
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL TO THE (E) KITCHEN TO REMOVE A LOAD BEARING WALL AND RELOCATED A BEDROOM
Permit Issued
Issued on 4/6/2021
Issuing Office
Current Status
Permit Finaled on 9/9/2021

Permit Application Status History

Submitted 3/11/2021 APPLICANT
Assigned to Plan Check Engineer 3/12/2021 MOHAMMAD ESMAILI
Corrections Issued 3/13/2021 MOHAMMAD ESMAILI
Building Plans Picked Up 3/18/2021 APPLICANT
Plan Check Approved 4/6/2021 MOHAMMAD ESMAILI
Issued 4/6/2021 APPLICANT
Permit Finaled 9/8/2021 RICHARD DOCKUS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Singh,, Jasbir; Lic. No.: C38767 16194 EASTRIDGE CT      CHINO HILLS, CA 91709

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/23/2021 Conditional Approval MISAEL ESPARZA
ELECTRICAL-Rough 4/30/2021 Approved MICHEL ABAJAN
Footing/Foundation/Slab 4/30/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 4/30/2021 Approved MICHEL ABAJAN
Wood Frame 4/30/2021 Corrections Issued MICHEL ABAJAN
Insulation 5/10/2021 Corrections Issued MICHAEL TEMPLE
Light Gage Steel Frame 5/10/2021 Not Ready for Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 5/25/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 6/7/2021 Approved MICHAEL TEMPLE
Final 9/8/2021 Permit Finaled RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 9/8/2021 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 9/8/2021 Approved RICHARD DOCKUS