6547-6549 N RIVERTON AVE 91606

Certificate Information: 6547-6549 N RIVERTON AVE 91606

Application / Permit
21016-20000-06001
Plan Check / Job No.
B21VN02767
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE INTO A (N) JR. ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.229
Permit Issued
Issued on 8/9/2021
Issuing Office
Current Status
CofO Issued on 4/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 SEAN SHAHMIRI
Corrections Issued 3/13/2021 SEAN SHAHMIRI
Building Plans Picked Up 3/19/2021 APPLICANT
Applicant returned to address corrections 4/26/2021 SEAN SHAHMIRI
Plan Check Approved 7/29/2021 SEAN SHAHMIRI
Issued 8/9/2021 APPLICANT
CofO in Progress 3/16/2023 JENNIFER RABUCHIN
Permit Finaled 4/4/2023 DANIEL ORRANTE
CofO Issued 4/4/2023 DANIEL ORRANTE
Permit Finaled 4/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/12/2021 GABRIEL ROBLES
Sewer availability Cleared 4/12/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 4/13/2021 GABRIEL ROBLES

Contact Information

Contractor American Home Improvement Inc; Lic. No.: 835537-B 20335 VENTURA BLVD #422      WOODLAND HILLS, CA 91364

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/31/2021 Approved DANIEL DREW
PLUMBING-Rough 8/31/2021 Partial Approval DANIEL DREW
ELECTRICAL-Rough 9/27/2021 Approved DANIEL DREW
Wood Frame 9/27/2021 Not Ready for Inspection DANIEL DREW
HVAC-Rough 10/4/2021 Approved CALEB MEISTER
Insulation 10/4/2021 Corrections Issued CALEB MEISTER
Interior/Exterior Lathing 10/7/2021 Approved DANIEL DREW
PLUMBING-Rough 10/7/2021 Approved DANIEL DREW
Shower Pan 10/7/2021 Approved DANIEL DREW
Wood Frame 10/7/2021 Approved DANIEL DREW
Drywall Nailing 10/13/2021 Approved DANIEL DREW
Final 2/10/2022 Corrections Issued MISAEL ESPARZA
Green Building Final 2/10/2022 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/10/2022 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 2/10/2022 Corrections Issued MISAEL ESPARZA
Final 2/23/2022 Corrections Issued MATT KELLERMAN
Green Building Final 2/23/2022 Approved MATT KELLERMAN
Smoke Detectors 2/23/2022 Corrections Issued MATT KELLERMAN
Final 5/24/2022 Corrections Issued JACK KARGODORIAN
Smoke Detectors 5/24/2022 Not Ready for Inspection JACK KARGODORIAN
Final 9/13/2022 No Access for Inspection JOHN HAYES
Smoke Detectors 9/13/2022 No Access for Inspection JOHN HAYES
ELECTRICAL-Final 11/22/2022 Approved JENNIFER RABUCHIN
Final 11/22/2022 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 11/22/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/22/2022 Approved JENNIFER RABUCHIN
Smoke Detectors 11/22/2022 Approved JENNIFER RABUCHIN