9581-9583 N GEYSER AVE 91324

Certificate Information: 9581-9583 N GEYSER AVE 91324

Application / Permit
21016-20000-05971
Plan Check / Job No.
B21VN02746
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d)(g) & VAULT CEILINGS PER ENG'R DESIGN
Permit Issued
Issued on 6/3/2021
Issuing Office
Current Status
CofO Issued on 4/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/17/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 NILOOFAR MEHRAIN
Corrections Issued 3/21/2021 NILOOFAR MEHRAIN
Building Plans Picked Up 3/25/2021 APPLICANT
Plan Check Approved 4/25/2021 NILOOFAR MEHRAIN
Issued 6/3/2021 APPLICANT
CofO in Progress 1/31/2025 DAVID SCANTLIN
Permit Finaled 4/11/2025 JOHN JANSON
CofO Issued 4/11/2025 JOHN JANSON
Permit Finaled 4/11/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/5/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/5/2021 ADRIAN CASTRO
Sewer availability Cleared 4/5/2021 ADRIAN CASTRO

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/24/2024 No Access for Inspection KRISTEN CAUSEY
PLUMBING-Rough 6/5/2024 Partial Approval KRISTEN CAUSEY
Footing/Foundation/Slab 6/13/2024 Approved DAVID SCANTLIN
ELECTRICAL-Rough 8/9/2024 Approved KRISTEN CAUSEY
PLUMBING-Rough 8/9/2024 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 8/28/2024 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 8/28/2024 Approved DAVID SCANTLIN
Green Building Rough 8/28/2024 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 8/28/2024 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 8/28/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 9/4/2024 Partial Inspection KRISTEN CAUSEY
Green Building Rough 9/4/2024 Partial Inspection KRISTEN CAUSEY
Shower Pan 9/4/2024 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 9/6/2024 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Partial Approval KRISTEN CAUSEY
Interior/Exterior Lathing 9/10/2024 Not Ready for Inspection KRISTEN CAUSEY
Insulation 9/16/2024 Partial Approval KRISTEN CAUSEY
Interior/Exterior Lathing 9/16/2024 Partial Approval KRISTEN CAUSEY
Drywall Nailing 9/23/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 9/23/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 10/18/2024 Approved DAVID SCANTLIN
Final 10/18/2024 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 10/18/2024 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 10/18/2024 Approved DAVID SCANTLIN
HVAC-Final 10/18/2024 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 10/18/2024 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 10/18/2024 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 10/18/2024 Not Ready for Inspection DAVID SCANTLIN
Final 11/25/2024 Corrections Issued DAVID SCANTLIN
Green Building Final 11/25/2024 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 11/25/2024 Approved DAVID SCANTLIN
Final 1/8/2025 Not Ready for Inspection KRISTEN CAUSEY
Final 1/21/2025 Not Ready for Inspection KRISTEN CAUSEY
Final 1/28/2025 Not Ready for Inspection KRISTEN CAUSEY
Final 1/30/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 1/30/2025 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 1/30/2025 SGSOV Approved DAVID SCANTLIN
Service/Power Release 2/5/2025 Approved DAVID SCANTLIN