6556 N MAMMOTH AVE 91401
Certificate Information: 6556 N MAMMOTH AVE 91401
- Application / Permit
- 21016-20000-05839
- Plan Check / Job No.
- B21VN02677
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-1" X 25'-6" DETACHED TWO-STORY GARAGE/RECREATION ROOM TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/14/2022
- Issuing Office
- Current Status
- CofO Issued on 12/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/31/2021 | JENNIFER LEE |
| Corrections Issued | 4/3/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 6/16/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 6/30/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 7/26/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 8/9/2021 | JENNIFER LEE |
| Applicant returned to address corrections | 9/28/2021 | JENNIFER LEE |
| Issued | 1/14/2022 | APPLICANT |
| Building Plans Picked Up | 1/19/2022 | APPLICANT |
| CofO in Progress | 11/27/2023 | ROBERT GOLD |
| No Progress | 12/5/2023 | ROBERT GOLD |
| CofO in Progress | 12/5/2023 | ROBERT GOLD |
| CofO in Progress | 12/19/2023 | RYAN SALAZAR |
| CofO Issued | 12/19/2023 | RUBEN SALAS |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2021 | ERIN MACIEL |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2021 | ERIN MACIEL |
| Permit | Cleared | 9/9/2021 | ERIN MACIEL |
| Sewer availability | Cleared | 9/9/2021 | ERIN MACIEL |
| Construction near power lines | Cleared | 12/29/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Houng,, Shao-Ming Paul; Lic. No.: C36602 | 16505 EMBER GLEN RD HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/18/2022 | Partial Approval | RICHARD DOCKUS |
| Footing/Foundation/Slab | 3/17/2022 | Corrections Issued | MICHAEL TEMPLE |
| Gas Test | 3/17/2022 | Approved | MICHAEL TEMPLE |
| PLUMBING-Rough | 3/17/2022 | Corrections Issued | MICHAEL TEMPLE |
| Pre-Inspection | 3/17/2022 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 3/22/2022 | Partial Approval | RICHARD DOCKUS |
| Wood Frame | 3/22/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 3/29/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/29/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/31/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 4/4/2022 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Rough | 4/4/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/11/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 4/11/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 4/11/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 4/18/2022 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Rough | 4/21/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Pre-Inspection | 5/12/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| HVAC-Rough | 7/13/2022 | Corrections Issued | RICHARD DOCKUS |
| Pre-Inspection | 7/13/2022 | Approved | RICHARD DOCKUS |
| Pre-Inspection | 9/15/2022 | Approved | RICHARD DOCKUS |
| Pre-Inspection | 12/28/2022 | No Access for Inspection | RYAN SALAZAR |
| Pre-Inspection | 12/30/2022 | Approved | RYAN SALAZAR |
| Pre-Inspection | 1/23/2023 | Partial Approval | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 1/27/2023 | Conditional Approval | JOHN COLEMAN |
| Insulation | 2/27/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 3/8/2023 | Approved | RYAN SALAZAR |
| Insulation | 3/8/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 3/24/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 7/21/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 8/7/2023 | Approved | RYAN SALAZAR |
| Green Building Final | 9/12/2023 | Not Ready for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | RYAN SALAZAR |
| Final | 10/16/2023 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 10/16/2023 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 10/16/2023 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 10/16/2023 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 10/25/2023 | SGSOV Not Ready | RYAN SALAZAR |
| Final | 11/1/2023 | Not Ready for Inspection | ROBERT GOLD |
| Green Building Final | 11/1/2023 | Not Ready for Inspection | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 11/1/2023 | SGSOV Not Ready | ROBERT GOLD |
| Smoke Detectors | 11/1/2023 | Not Ready for Inspection | ROBERT GOLD |
| Final | 11/8/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 11/8/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 11/8/2023 | Approved | RYAN SALAZAR |
| Service/Power Release | 12/5/2023 | Approved | RYAN SALAZAR |
| Final | 12/6/2023 | Corrections Issued | RYAN SALAZAR |
| Final | 12/20/2023 | OK to Issue CofO | RYAN SALAZAR |