1623 W DEL AMO BLVD 90501
Certificate Information: 1623 W DEL AMO BLVD 90501
- Application / Permit
- 21016-20000-05759
- Plan Check / Job No.
- B21VN02613
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 20' x 31' GARAGE INTO A NEW IRREGULAR 20'-0" x 31'-0" ACCESSORY DWELLING UNIT AND A 5'-7" x 9'-10" LAUNDRY AREA. per LAMC 12.22 A.33(c)¹, (d)¹, and (g), ALL WORK PER WFPP
- Permit Issued
- Issued on 6/2/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2021 | LUIS RINCON |
| Corrections Issued | 3/15/2021 | LUIS RINCON |
| Building Plans Picked Up | 3/25/2021 | APPLICANT |
| Plan Check Approved | 5/31/2021 | MOHAMMAD ESMAILI |
| Issued | 6/2/2021 | APPLICANT |
| CofO in Progress | 4/15/2022 | EUGENE CASSIDY |
| Permit Finaled | 4/19/2022 | DEROLD HAUFF |
| CofO Issued | 4/19/2022 | DEROLD HAUFF |
| Permit Finaled | 4/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/11/2021 | CHINH DINH |
| "Q" conditions | Cleared | 5/12/2021 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2021 | CHINH DINH |
| ZI | Cleared | 5/19/2021 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/21/2021 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 9/23/2021 | Corrections Issued | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/6/2021 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 10/6/2021 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 10/6/2021 | Partial Approval | JOHN KLARIN |
| Deputy Drilled-In Anchors | 10/15/2021 | No Access for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 10/22/2021 | Not Ready for Inspection | JOHN KLARIN |
| Green Building Rough | 10/22/2021 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 10/22/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/5/2021 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 11/5/2021 | Partial Approval | JOHN KLARIN |
| HVAC-Rough | 11/5/2021 | Approved | JOHN KLARIN |
| Pre-Inspection | 11/5/2021 | Conditional Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/9/2021 | Corrections Issued | JOHN KLARIN |
| Green Building Rough | 11/9/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 11/10/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/29/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 11/29/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 1/6/2022 | Partial Approval | JOHN KLARIN |
| ELECTRICAL-Final | 1/28/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 1/28/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Interior/Exterior Lathing | 1/28/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/9/2022 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 3/9/2022 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Final | 3/9/2022 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/30/2022 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 3/30/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 3/30/2022 | Approved | EUGENE CASSIDY |
| Green Building Final | 4/4/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/6/2022 | Approved | EUGENE CASSIDY |
| Final | 4/6/2022 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/6/2022 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 4/6/2022 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/14/2022 | Approved | EUGENE CASSIDY |
| Final | 4/14/2022 | OK to Issue CofO | EUGENE CASSIDY |