832-834 N LAGOON AVE 90744

Certificate Information: 832-834 N LAGOON AVE 90744

Application / Permit
21016-20000-05553
Plan Check / Job No.
B21VN02517
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED 20' X 20' GARAGE TO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). WORK PER WFPP.
Permit Issued
Issued on 11/17/2021
Issuing Office
Current Status
CofO Issued on 8/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2021 APPLICANT
Assigned to Plan Check Engineer 3/10/2021 GURUNATH NESARAJAH
Corrections Issued 3/10/2021 GURUNATH NESARAJAH
Plan Check Approved 11/3/2021 ROSENDO MEDINA
Building Plans Picked Up 11/4/2021 APPLICANT
Issued 11/17/2021 APPLICANT
CofO in Progress 8/5/2022 EUGENE CASSIDY
Permit Finaled 8/20/2022 DEROLD HAUFF
CofO Issued 8/20/2022 DEROLD HAUFF
Permit Finaled 8/20/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/20/2021 JOSE HERNANDEZ
Sewer availability Cleared 7/20/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 7/27/2021 JOSE HERNANDEZ
"Q" conditions Cleared 10/15/2021 MAXFIELD VERMY
Clean Up Green Up Cleared 10/15/2021 MAXFIELD VERMY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/23/2021 Partial Approval JOHN KLARIN
Sewer 11/23/2021 Approved JOHN KLARIN
Footing/Foundation/Slab 12/10/2021 Corrections Issued JOHN KLARIN
Wood Frame 1/11/2022 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Rough 3/24/2022 Approved EUGENE CASSIDY
HVAC-Rough 3/24/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 3/24/2022 Approved EUGENE CASSIDY
Wood Frame 3/24/2022 Approved EUGENE CASSIDY
Insulation 3/31/2022 Corrections Issued EUGENE CASSIDY
Insulation 4/6/2022 Approved EUGENE CASSIDY
Drywall Nailing 4/22/2022 Approved EUGENE CASSIDY
Shower Pan 4/22/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/10/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/30/2022 Not Ready for Inspection EUGENE CASSIDY
Final 6/30/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 6/30/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 6/30/2022 Approved EUGENE CASSIDY
METHANE-Final 6/30/2022 Approved EUGENE CASSIDY
METHANE-Rough 6/30/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 6/30/2022 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 7/29/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 7/29/2022 Not Ready for Inspection EUGENE CASSIDY
Final 7/29/2022 Corrections Issued EUGENE CASSIDY
Gas Test 7/29/2022 Approved EUGENE CASSIDY
Green Building Final 7/29/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 7/29/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/5/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/5/2022 Approved EUGENE CASSIDY
Final 8/5/2022 OK to Issue CofO EUGENE CASSIDY
Green Building Final 8/5/2022 Approved EUGENE CASSIDY
HVAC-Final 8/5/2022 Approved EUGENE CASSIDY
PLUMBING-Final 8/5/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/5/2022 SGSOV Approved EUGENE CASSIDY