14820-14822 W MORRISON ST 91403
Certificate Information: 14820-14822 W MORRISON ST 91403
- Application / Permit
- 21016-20000-05498
- Plan Check / Job No.
- B21VN02499
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL TO (E) SFD. WINDOWS CHANGEOUT (SAME SIZE AND SAME LOCATION). REMOVE ATTACHED CARPORT AND ADD (262 SF) (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e) . ADD (79 SF) FOR (N) ENTRY/FOYER. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/18/2021
- Issuing Office
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/9/2021 | RAPHAEL ROSAS |
| Corrections Issued | 4/10/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/8/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/19/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 8/5/2021 | RAPHAEL ROSAS |
| Issued | 8/18/2021 | APPLICANT |
| Building Plans Picked Up | 8/18/2021 | APPLICANT |
| CofO in Progress | 5/12/2022 | JACK KARGODORIAN |
| Permit Finaled | 5/21/2022 | MICHAEL SMITH |
| CofO Issued | 5/21/2022 | MICHAEL SMITH |
| Permit Finaled | 5/21/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| ZI | Cleared | 4/26/2021 | PABLO ESTRADA |
| Address approval | Cleared | 8/11/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/11/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/11/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/17/2021 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 11/18/2021 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 11/30/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 11/30/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| MERV13>=Rough | 11/30/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 12/13/2021 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 12/13/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 12/13/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| MERV13>=Rough | 12/13/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 12/13/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/13/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 1/13/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 1/13/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 1/13/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 1/13/2022 | Partial Approval | JACK KARGODORIAN |
| MERV13>=Rough | 1/13/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 1/13/2022 | Approved | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 1/13/2022 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/27/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 1/27/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 2/8/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 2/8/2022 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 2/15/2022 | Approved | JACK KARGODORIAN |
| Insulation | 2/15/2022 | Corrections Issued | JACK KARGODORIAN |
| Insulation | 2/18/2022 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 2/23/2022 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 3/10/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/15/2022 | Partial Approval | JACK KARGODORIAN |
| Final | 4/29/2022 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 4/29/2022 | Approved | JACK KARGODORIAN |
| Green Building Final | 4/29/2022 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 4/29/2022 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/29/2022 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 4/29/2022 | Approved | JACK KARGODORIAN |
| Final | 5/3/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/3/2022 | SGSOV Not Ready | ARAM AVEDISIAN |
| Pre-Inspection | 5/5/2022 | Corrections Issued | MISAEL ESPARZA |
| Service/Power Release | 5/5/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 5/12/2022 | OK to Issue CofO | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 5/12/2022 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 5/12/2022 | Approved | JACK KARGODORIAN |