19940 W CALVERT ST 91367

Certificate Information: 19940 W CALVERT ST 91367

Application / Permit
21016-20000-05496
Plan Check / Job No.
B21VN02498
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 30' X 32'DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ENGINEER.
Permit Issued
Issued on 9/23/2021
Issuing Office
Current Status
CofO Issued on 12/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2021 APPLICANT
Assigned to Plan Check Engineer 3/31/2021 PARISA ZAHABI
Corrections Issued 3/31/2021 PARISA ZAHABI
Building Plans Picked Up 4/14/2021 APPLICANT
Applicant returned to address corrections 7/19/2021 PARISA ZAHABI
Applicant returned to address corrections 8/4/2021 PARISA ZAHABI
Issued 9/23/2021 APPLICANT
CofO in Progress 10/19/2022 SEAN HAUPT
CofO Issued 12/6/2022 JOHN JANSON
Permit Finaled 12/6/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/22/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 6/22/2021 GABRIEL ROBLES
Sewer availability Cleared 6/22/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/28/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/7/2022 Partial Approval SEAN HAUPT
Gas Test 1/7/2022 Approved SEAN HAUPT
PLUMBING-Rough 1/7/2022 Partial Approval SEAN HAUPT
Sewer 1/7/2022 Approved SEAN HAUPT
Deputy Drilled-In Anchors 2/18/2022 Conditional Approval MORRIS JACKSON
Footing/Foundation/Slab 2/28/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 4/7/2022 Partial Approval SEAN HAUPT
ELECTRICAL-Rough 4/7/2022 Approved SEAN HAUPT
PLUMBING-Rough 4/7/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Approved SEAN HAUPT
Insulation 4/19/2022 Partial Approval SEAN HAUPT
Interior/Exterior Lathing 4/19/2022 Approved SEAN HAUPT
Insulation 4/21/2022 Approved SEAN HAUPT
Shower Pan 4/21/2022 Not Ready for Inspection SEAN HAUPT
Drywall Nailing 4/27/2022 Approved SEAN HAUPT
Shower Pan 4/27/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 5/4/2022 Approved MORRIS JACKSON
BUILDING-Rough-Frame 9/29/2022 Approved SEAN HAUPT
Final 9/29/2022 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 9/29/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 9/29/2022 Approved SEAN HAUPT
Final 10/18/2022 OK to Issue CofO SEAN HAUPT
Service/Power Release 10/18/2022 Approved SEAN HAUPT