8141 N GARDEN GROVE AVE 91335
Certificate Information: 8141 N GARDEN GROVE AVE 91335
- Application / Permit
- 21016-20000-05444
- Plan Check / Job No.
- B21VN02445
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX 18'3"X37' DET GARAGE INTO 18'3"X7' STORAGE RM & 18'3"X30' ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 8/25/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2021 | PINANK PATEL |
| Corrections Issued | 3/8/2021 | PINANK PATEL |
| Building Plans Picked Up | 3/9/2021 | APPLICANT |
| Plan Check Approved | 4/19/2023 | HAYATO TSUCHIYA |
| Issued | 8/25/2023 | APPLICANT |
| CofO in Progress | 5/22/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 6/16/2025 | JOHN JANSON |
| CofO Issued | 6/16/2025 | JOHN JANSON |
| Permit Finaled | 6/16/2025 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/15/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/15/2022 | RIDWAN HARDY |
| Address approval | Cleared | 3/17/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/17/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2022 | CARLOS AGUILERA |
| ZA Case | Cleared | 11/7/2022 | ASHLEY RODARTE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/7/2024 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 12/17/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/17/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Deputy Drilled-In Anchors | 12/18/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 12/30/2024 | Corrections Issued | JOHN COLEMAN |
| Underground Mechanical | 12/30/2024 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 1/21/2025 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 1/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Underground Mechanical | 1/21/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 1/24/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 1/24/2025 | Partial Approval | ARUTYUN MADATYAN |
| Underground Mechanical | 1/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 2/11/2025 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 2/24/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 2/24/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 2/24/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 2/24/2025 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 2/24/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 2/27/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 3/4/2025 | Not Ready for Inspection | MORRIS JACKSON |
| Drywall Nailing | 3/7/2025 | Approved | GEVORK IPCHYAN |
| Shower Pan | 3/7/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 3/11/2025 | Partial Approval | ARUTYUN MADATYAN |
| Underground Mechanical | 3/11/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 4/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 4/14/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 4/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 4/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Final | 4/14/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 4/14/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 4/14/2025 | Approved | ARUTYUN MADATYAN |
| Final | 4/18/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Green Building Final | 4/18/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Pre-Inspection | 4/25/2025 | Partial Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 5/6/2025 | Partial Approval | ARUTYUN MADATYAN |
| Pre-Inspection | 5/6/2025 | Partial Inspection | ARUTYUN MADATYAN |
| Final | 5/20/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 5/20/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 5/22/2025 | Approved | ARUTYUN MADATYAN |
| Final | 5/22/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 5/22/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 5/22/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 5/22/2025 | Approved | ARUTYUN MADATYAN |