5820 N CALVIN AVE 91356
Certificate Information: 5820 N CALVIN AVE 91356
- Application / Permit
- 21016-20000-05403
- Plan Check / Job No.
- B21VN02425
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED 42' 10" X 24' 11" IRR.-SHAPE GARAGE/REC ROOM/STORAGE TO ADU PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 5/25/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 3/24/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 4/9/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 4/29/2021 | JESSE ARELLANO |
| Plan Check Approved | 5/11/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 5/11/2021 | APPLICANT |
| Issued | 5/25/2021 | APPLICANT |
| CofO in Progress | 2/25/2022 | SEAN HAUPT |
| CofO in Progress | 2/28/2022 | SEAN HAUPT |
| CofO Issued | 3/6/2022 | MICHAEL SMITH |
| Permit Finaled | 3/6/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hold | Cleared | 3/17/2021 | JASON SHEETS |
| Address approval | Cleared | 3/30/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 3/30/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/13/2021 | GUILLERMO PETRA |
| ZI | Cleared | 4/16/2021 | MARITZA PRZEKOP |
| Green Code | Cleared | 5/11/2021 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/14/2021 | Corrections Issued | STEVEN BACK |
| Pre-Inspection | 7/14/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 7/28/2021 | Approved | STEVEN BACK |
| Pre-Inspection | 7/28/2021 | Partial Inspection | STEVEN BACK |
| PLUMBING-Rough | 8/25/2021 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 9/16/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 9/16/2021 | Corrections Issued | STEVEN BACK |
| Underground Mechanical | 9/16/2021 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 9/24/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 9/24/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 10/5/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 10/5/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2021 | Approved | STEVEN BACK |
| Green Building Rough | 10/5/2021 | Not Ready for Inspection | STEVEN BACK |
| MERV13>=Rough | 10/5/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 10/19/2021 | Approved | SEAN HAUPT |
| HVAC-Rough | 11/5/2021 | Approved | SEAN HAUPT |
| Insulation | 11/5/2021 | Approved | SEAN HAUPT |
| Drywall Nailing | 11/12/2021 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 11/29/2021 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/16/2021 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 12/16/2021 | Approved | SEAN HAUPT |
| Final | 12/16/2021 | Conditional Approval | SEAN HAUPT |
| Green Building Final | 12/16/2021 | Approved | SEAN HAUPT |
| Green Building Rough | 12/16/2021 | Approved | SEAN HAUPT |
| HVAC-Final | 12/16/2021 | Approved | SEAN HAUPT |
| MERV13>=Final | 12/16/2021 | Approved | SEAN HAUPT |
| PLUMBING-Final | 12/16/2021 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/16/2021 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 12/16/2021 | Approved | SEAN HAUPT |
| Final | 12/22/2021 | Corrections Issued | SEAN HAUPT |
| Final | 2/25/2022 | Partial Approval | SEAN HAUPT |