5423 1/2-3/4 E ASH ST 90042

Certificate Information: 5423 1/2-3/4 E ASH ST 90042

Application / Permit
21016-20000-05387
Plan Check / Job No.
B21VN02421
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT (E) SFD TO (N) DUPLEX (REAR BLDG) [NFPA-13D FIRE SPRINKLERS THROUGHOUT]
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
CofO Issued on 8/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/18/2021 NILOOFAR MEHRAIN
Corrections Issued 3/24/2021 NILOOFAR MEHRAIN
Quality Review Completed 3/25/2021 CHON CHIO KUO
Plan Check Approved 6/16/2021 NILOOFAR MEHRAIN
Issued 7/1/2021 APPLICANT
CofO in Progress 8/11/2022 HAMIK HARTOUNIAN
Permit Finaled 8/20/2022 DEROLD HAUFF
CofO Issued 8/20/2022 DEROLD HAUFF
Permit Finaled 8/20/2022 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 4/7/2021 KATIE DEBIASE
HPOZ Cleared 4/7/2021 KATIE DEBIASE
Miscellaneous Cleared 4/7/2021 KATIE DEBIASE
ZI Cleared 4/7/2021 KATIE DEBIASE
Address approval Cleared 4/8/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 4/12/2021 WALLIE JONG
Sewer availability Cleared 4/12/2021 WALLIE JONG
Hydrant and Access approval Cleared 5/23/2021 ROBERT DUFF

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/1/2021 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 9/1/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 9/1/2021 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 9/1/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Wood Frame 9/1/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Pre-Inspection 9/3/2021 Approved HORACE FULTZ
PLUMBING-Rough 9/16/2021 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 9/22/2021 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/15/2021 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 10/15/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 10/15/2021 Approved HAMIK HARTOUNIAN
Wood Frame 10/15/2021 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/22/2021 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 10/22/2021 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/16/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 11/16/2021 Corrections Issued HAMIK HARTOUNIAN
Underground Mechanical 11/17/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 11/30/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/6/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 12/6/2021 Approved HAMIK HARTOUNIAN
Insulation 12/6/2021 Approved HAMIK HARTOUNIAN
Wood Frame 12/6/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 1/27/2022 Approved HAMIK HARTOUNIAN
Shower Pan 1/27/2022 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Final 4/20/2022 Approved HAMIK HARTOUNIAN
HVAC-Final 4/20/2022 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 4/20/2022 Approved HAMIK HARTOUNIAN
Final 4/26/2022 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/26/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 4/26/2022 Approved HAMIK HARTOUNIAN
Final 5/19/2022 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/19/2022 SGSOV Approved HAMIK HARTOUNIAN
Special/Order Compliance 7/27/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 8/5/2022 Approved HAMIK HARTOUNIAN
Final 8/5/2022 OK to Issue CofO HAMIK HARTOUNIAN
HVAC-Final 8/5/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Final 8/5/2022 Approved HAMIK HARTOUNIAN