16627 1/2 W VICTORY BLVD 91406

Certificate Information: 16627 1/2 W VICTORY BLVD 91406

Application / Permit
21016-20000-05265
Plan Check / Job No.
B21VN02398
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) DETACHED REC. ROOM INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 4/5/2021
Issuing Office
Current Status
CofO Issued on 1/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/2/2021 APPLICANT
Assigned to Plan Check Engineer 3/8/2021 ANGELICA DAVE
Corrections Issued 3/8/2021 ANGELICA DAVE
Plan Check Approved 3/24/2021 ANGELICA MARTINEZ
Issued 4/5/2021 APPLICANT
Building Plans Picked Up 4/5/2021 APPLICANT
CofO in Progress 1/9/2025 SALVADOR MARTINEZ
CofO Issued 1/24/2025 RUBEN SALAS
Permit Finaled 1/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/11/2021 GABRIEL ROBLES
Sewer availability Cleared 3/11/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 3/15/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/23/2021 Approved JACK KARGODORIAN
Footing/Foundation/Slab 10/4/2021 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 10/4/2021 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 1/4/2022 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 1/6/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 2/4/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 2/4/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/4/2022 Approved RAUL OLAGI
PLUMBING-Rough 2/4/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 2/10/2022 Approved RAUL OLAGI
ELECTRICAL-Rough 2/10/2022 Approved RAUL OLAGI
Green Building Rough 2/10/2022 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 2/10/2022 Approved RAUL OLAGI
Insulation 2/10/2022 Approved RAUL OLAGI
PLUMBING-Rough 2/10/2022 Approved RAUL OLAGI
Drywall Nailing 2/18/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/18/2022 Approved JESUS RODRIGUEZ
Shower Pan 2/18/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 9/17/2024 Approved RAUL OLAGI
ELECTRICAL-Final 9/17/2024 Corrections Issued RAUL OLAGI
Final 9/17/2024 Corrections Issued RAUL OLAGI
Green Building Final 9/17/2024 Approved RAUL OLAGI
Green Building Rough 9/17/2024 Approved RAUL OLAGI
HVAC-Final 9/17/2024 Corrections Issued RAUL OLAGI
PLUMBING-Final 9/17/2024 Corrections Issued RAUL OLAGI
Smoke Detectors 9/17/2024 Approved RAUL OLAGI
Final 11/5/2024 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 11/5/2024 SGSOV Approved SALVADOR MARTINEZ
Final 12/5/2024 Corrections Issued SALVADOR MARTINEZ
Final 1/6/2025 OK to Issue CofO SALVADOR MARTINEZ