16627 1/2 W VICTORY BLVD 91406
Certificate Information: 16627 1/2 W VICTORY BLVD 91406
- Application / Permit
- 21016-20000-05265
- Plan Check / Job No.
- B21VN02398
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED REC. ROOM INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/5/2021
- Issuing Office
- Current Status
- CofO Issued on 1/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2021 | ANGELICA DAVE |
| Corrections Issued | 3/8/2021 | ANGELICA DAVE |
| Plan Check Approved | 3/24/2021 | ANGELICA MARTINEZ |
| Issued | 4/5/2021 | APPLICANT |
| Building Plans Picked Up | 4/5/2021 | APPLICANT |
| CofO in Progress | 1/9/2025 | SALVADOR MARTINEZ |
| CofO Issued | 1/24/2025 | RUBEN SALAS |
| Permit Finaled | 1/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/11/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/23/2021 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 10/4/2021 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Rough | 10/4/2021 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 1/4/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 1/6/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/4/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 2/4/2022 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 2/4/2022 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/10/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 2/10/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 2/10/2022 | Not Ready for Inspection | RAUL OLAGI |
| HVAC-Rough | 2/10/2022 | Approved | RAUL OLAGI |
| Insulation | 2/10/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 2/10/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 2/18/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/18/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 2/18/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/17/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 9/17/2024 | Corrections Issued | RAUL OLAGI |
| Final | 9/17/2024 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 9/17/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 9/17/2024 | Approved | RAUL OLAGI |
| HVAC-Final | 9/17/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 9/17/2024 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 9/17/2024 | Approved | RAUL OLAGI |
| Final | 11/5/2024 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 11/5/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Final | 12/5/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 1/6/2025 | OK to Issue CofO | SALVADOR MARTINEZ |