919 1/2 W 53RD ST 90037

Certificate Information: 919 1/2 W 53RD ST 90037

Application / Permit
21016-20000-05196
Plan Check / Job No.
B21VN02369
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 4/27/2021
Issuing Office
Current Status
CofO Issued on 3/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 SELLA BENYAMIN
Corrections Issued 3/8/2021 SELLA BENYAMIN
Plan Check Approved 3/17/2021 LUISANGEL VALENZUELA
Building Plans Picked Up 3/18/2021 APPLICANT
Issued 4/27/2021 APPLICANT
CofO in Progress 3/23/2023 STUART CHAPMAN
Permit Finaled 3/25/2023 DEROLD HAUFF
CofO Issued 3/25/2023 DEROLD HAUFF
Permit Finaled 3/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/10/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 3/10/2021 ROSA SILVA
Roof/Waste drainage to street Cleared 3/10/2021 ROSA SILVA
Sewer availability Cleared 3/10/2021 ROSA SILVA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/15/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 9/22/2022 Partial Approval SABAS ALONSO
Underground Mechanical 9/22/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 10/5/2022 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 10/11/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 10/11/2022 Approved STUART CHAPMAN
PLUMBING-Rough 10/11/2022 Partial Approval STUART CHAPMAN
Underground Mechanical 10/11/2022 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 10/17/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 10/17/2022 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Approved SABAS ALONSO
Green Building Rough 10/17/2022 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 10/17/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 10/24/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 10/24/2022 Approved SABAS ALONSO
Green Building Rough 10/24/2022 Approved SABAS ALONSO
HVAC-Rough 10/24/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 10/24/2022 Partial Approval SABAS ALONSO
Insulation 10/31/2022 Approved SABAS ALONSO
Drywall Nailing 11/3/2022 Approved SABAS ALONSO
Underground Mechanical 12/20/2022 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 12/27/2022 Partial Approval SABAS ALONSO
ELECTRICAL-Final 3/7/2023 Approved STUART CHAPMAN
Final 3/7/2023 Corrections Issued STUART CHAPMAN
Green Building Final 3/7/2023 Approved STUART CHAPMAN
HVAC-Final 3/7/2023 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Final 3/7/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Approved STUART CHAPMAN
Service/Power Release 3/7/2023 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 3/7/2023 Approved STUART CHAPMAN
ELECTRICAL-Final 3/23/2023 Approved STUART CHAPMAN
Final 3/23/2023 OK to Issue CofO STUART CHAPMAN
HVAC-Final 3/23/2023 Approved STUART CHAPMAN