919 1/2 W 53RD ST 90037
Certificate Information: 919 1/2 W 53RD ST 90037
- Application / Permit
- 21016-20000-05196
- Plan Check / Job No.
- B21VN02369
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 4/27/2021
- Issuing Office
- Current Status
- CofO Issued on 3/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | SELLA BENYAMIN |
| Corrections Issued | 3/8/2021 | SELLA BENYAMIN |
| Plan Check Approved | 3/17/2021 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 3/18/2021 | APPLICANT |
| Issued | 4/27/2021 | APPLICANT |
| CofO in Progress | 3/23/2023 | STUART CHAPMAN |
| Permit Finaled | 3/25/2023 | DEROLD HAUFF |
| CofO Issued | 3/25/2023 | DEROLD HAUFF |
| Permit Finaled | 3/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2021 | ROSA SILVA |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2021 | ROSA SILVA |
| Roof/Waste drainage to street | Cleared | 3/10/2021 | ROSA SILVA |
| Sewer availability | Cleared | 3/10/2021 | ROSA SILVA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/15/2022 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 9/22/2022 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 9/22/2022 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 10/5/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 10/11/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/11/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 10/11/2022 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 10/11/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/17/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 10/17/2022 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 10/17/2022 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 10/17/2022 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/24/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 10/24/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 10/24/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 10/24/2022 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 10/24/2022 | Partial Approval | SABAS ALONSO |
| Insulation | 10/31/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 11/3/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 12/20/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/27/2022 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Final | 3/7/2023 | Approved | STUART CHAPMAN |
| Final | 3/7/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 3/7/2023 | Approved | STUART CHAPMAN |
| HVAC-Final | 3/7/2023 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 3/7/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 3/7/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 3/7/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 3/23/2023 | Approved | STUART CHAPMAN |
| Final | 3/23/2023 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 3/23/2023 | Approved | STUART CHAPMAN |