5210-5212 N VELOZ AVE 91356
Certificate Information: 5210-5212 N VELOZ AVE 91356
- Application / Permit
- 21016-20000-05133
- Plan Check / Job No.
- B21VN02355
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL TO (E) SFD, AND CONVERT (E) ATTACHED GARAGE TO ADU PER LAMC 12.22 A.33(c) AND ADD NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/28/2021
- Issuing Office
- Current Status
- CofO Issued on 11/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2021 | PETER MOSESIAN |
| Corrections Issued | 3/31/2021 | PETER MOSESIAN |
| Quality Review Completed | 4/15/2021 | OMID HEDAYAT |
| Plan Check Approved | 5/27/2021 | PETER MOSESIAN |
| Issued | 5/28/2021 | APPLICANT |
| Permit Finaled | 11/29/2025 | MICHAEL PELHAM |
| CofO Issued | 11/29/2025 | MICHAEL PELHAM |
| Permit Finaled | 11/29/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2021 | ADRIAN CASTRO |
| Address approval | Cleared | 4/19/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/19/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 4/19/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/19/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 6/23/2021 | Partial Approval | DAVID SANDOVAL |
| ELECTRICAL-Rough | 6/30/2021 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 6/30/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 6/30/2021 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 7/9/2021 | Approved | RYAN SALAZAR |
| Insulation | 7/9/2021 | Corrections Issued | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/12/2021 | Not Ready for Inspection | RYAN SALAZAR |
| Insulation | 7/13/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/13/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/19/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Shower Pan | 7/19/2021 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 7/22/2021 | Approved | RYAN SALAZAR |
| Green Building Rough | 7/22/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 7/22/2021 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/13/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Final | 10/13/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 10/13/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 10/13/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Final | 10/13/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Final | 10/13/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 10/13/2021 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 10/13/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Final | 10/21/2021 | Approved | DAVID SANDOVAL |
| Final | 10/21/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Gas Test | 10/21/2021 | Approved | DAVID SANDOVAL |
| Green Building Final | 10/21/2021 | Approved | DAVID SANDOVAL |
| HVAC-Final | 10/21/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 10/21/2021 | Approved | DAVID SANDOVAL |
| Smoke Detectors | 10/21/2021 | Approved | DAVID SANDOVAL |
| Final | 11/8/2021 | Partial Approval | DAVID SANDOVAL |
| Service/Power Release | 7/15/2024 | Approved | SEAN WIRCH |