5210-5212 N VELOZ AVE 91356

Certificate Information: 5210-5212 N VELOZ AVE 91356

Application / Permit
21016-20000-05133
Plan Check / Job No.
B21VN02355
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO (E) SFD, AND CONVERT (E) ATTACHED GARAGE TO ADU PER LAMC 12.22 A.33(c) AND ADD NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/28/2021
Issuing Office
Current Status
CofO Issued on 11/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2021 APPLICANT
Assigned to Plan Check Engineer 3/25/2021 PETER MOSESIAN
Corrections Issued 3/31/2021 PETER MOSESIAN
Quality Review Completed 4/15/2021 OMID HEDAYAT
Plan Check Approved 5/27/2021 PETER MOSESIAN
Issued 5/28/2021 APPLICANT
Permit Finaled 11/29/2025 MICHAEL PELHAM
CofO Issued 11/29/2025 MICHAEL PELHAM
Permit Finaled 11/29/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 4/19/2021 ADRIAN CASTRO
Address approval Cleared 4/19/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/19/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 4/19/2021 ADRIAN CASTRO
Sewer availability Cleared 4/19/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/14/2021 Approved DAVID SANDOVAL
PLUMBING-Rough 6/23/2021 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 6/30/2021 Approved DAVID SANDOVAL
HVAC-Rough 6/30/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 6/30/2021 Approved DAVID SANDOVAL
HVAC-Rough 7/9/2021 Approved RYAN SALAZAR
Insulation 7/9/2021 Corrections Issued RYAN SALAZAR
Interior/Exterior Lathing 7/12/2021 Not Ready for Inspection RYAN SALAZAR
Insulation 7/13/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/13/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/19/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
Shower Pan 7/19/2021 Approved ALIZAH MAYAGOITIA
Drywall Nailing 7/22/2021 Approved RYAN SALAZAR
Green Building Rough 7/22/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 7/22/2021 Approved RYAN SALAZAR
BUILDING-Rough-Frame 10/13/2021 Approved DAVID SANDOVAL
ELECTRICAL-Final 10/13/2021 Not Ready for Inspection DAVID SANDOVAL
Final 10/13/2021 Corrections Issued DAVID SANDOVAL
Green Building Final 10/13/2021 Not Ready for Inspection DAVID SANDOVAL
HVAC-Final 10/13/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Final 10/13/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 10/13/2021 SGSOV Approved DAVID SANDOVAL
Smoke Detectors 10/13/2021 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Final 10/21/2021 Approved DAVID SANDOVAL
Final 10/21/2021 Not Ready for Inspection DAVID SANDOVAL
Gas Test 10/21/2021 Approved DAVID SANDOVAL
Green Building Final 10/21/2021 Approved DAVID SANDOVAL
HVAC-Final 10/21/2021 Approved DAVID SANDOVAL
PLUMBING-Final 10/21/2021 Approved DAVID SANDOVAL
Smoke Detectors 10/21/2021 Approved DAVID SANDOVAL
Final 11/8/2021 Partial Approval DAVID SANDOVAL
Service/Power Release 7/15/2024 Approved SEAN WIRCH