7155-7157 N FALLBROOK AVE 91307
Certificate Information: 7155-7157 N FALLBROOK AVE 91307
- Application / Permit
- 21016-20000-05081
- Plan Check / Job No.
- B21VN02328
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) 20 X 20 ATTACHED GARGAE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 4/26/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | SELLA BENYAMIN |
| Corrections Issued | 3/8/2021 | SELLA BENYAMIN |
| Building Plans Picked Up | 3/10/2021 | APPLICANT |
| Plan Check Approved | 4/23/2021 | SELLA BENYAMIN |
| Issued | 4/26/2021 | APPLICANT |
| CofO in Progress | 4/27/2022 | CHRIS CHRISTENSEN |
| Permit Finaled | 5/21/2022 | MICHAEL SMITH |
| CofO Issued | 5/21/2022 | MICHAEL SMITH |
| Permit Finaled | 5/21/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/10/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/10/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/19/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 7/19/2021 | Partial Approval | DAVID STEPANYAN |
| Sewer | 7/19/2021 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/1/2021 | Partial Inspection | DAVID SANDOVAL |
| Green Building Rough | 11/12/2021 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 11/12/2021 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 11/12/2021 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 11/18/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 11/18/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 11/18/2021 | Approved | DAVID STEPANYAN |
| Insulation | 11/19/2021 | Corrections Issued | DAVID STEPANYAN |
| Drywall Nailing | 11/23/2021 | Approved | DAVID STEPANYAN |
| Insulation | 11/23/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 4/13/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 4/13/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 4/13/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 4/13/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 4/13/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 4/13/2022 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Service/Power Release | 4/13/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 4/13/2022 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 4/26/2022 | Approved | CHRIS CHRISTENSEN |
| Final | 4/26/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| HVAC-Final | 4/26/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 4/26/2022 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 4/26/2022 | SGSOV Approved | CHRIS CHRISTENSEN |