1807 S POINT VIEW ST 90035
Certificate Information: 1807 S POINT VIEW ST 90035
- Application / Permit
- 21016-20000-04988
- Plan Check / Job No.
- B21VN02275
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A); ALL WORK PER WFPP
- Permit Issued
- Issued on 3/31/2021
- Issuing Office
- Current Status
- CofO Issued on 7/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | SEAN SHAHMIRI |
| Corrections Issued | 3/7/2021 | SEAN SHAHMIRI |
| Building Plans Picked Up | 3/10/2021 | APPLICANT |
| Plan Check Approved | 3/31/2021 | SEAN SHAHMIRI |
| Issued | 3/31/2021 | APPLICANT |
| CofO in Progress | 3/22/2022 | JOSE AVILA |
| No Progress | 4/25/2022 | JOSE AVILA |
| CofO in Progress | 4/25/2022 | JOSE AVILA |
| Permit Finaled | 7/5/2022 | DEROLD HAUFF |
| CofO Issued | 7/5/2022 | DEROLD HAUFF |
| Permit Finaled | 7/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/12/2021 | JUAN ASHTON |
| Sewer availability | Cleared | 3/12/2021 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | JUAN ASHTON |
Contact Information
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | 21204 VANOWEN STREET CANOGA PARK, CA 91303 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/25/2021 | Partial Approval | STUART CHAPMAN |
| Sewer | 6/25/2021 | Approved | STUART CHAPMAN |
| Underground Mechanical | 6/25/2021 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 7/7/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 7/22/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 7/22/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Rough-Elec/Plmb/HVAC | 7/22/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 7/29/2021 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 7/29/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 7/29/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 8/4/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Rough-Elec/Plmb/HVAC | 8/4/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/10/2021 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 8/10/2021 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 8/10/2021 | Approved | KATHRYN BUTTERWORTH |
| Rough-Elec/Plmb/HVAC | 8/10/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 8/13/2021 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 8/13/2021 | Approved | CALEB MEISTER |
| Rough-Elec/Plmb/HVAC | 8/13/2021 | Approved | CALEB MEISTER |
| Pre-Inspection | 8/24/2021 | Partial Approval | ASHLEY THOMPSON |
| Shower Pan | 8/24/2021 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 9/1/2021 | Partial Approval | SCOTT FINNILA |
| PLUMBING-Rough | 9/1/2021 | Partial Inspection | SCOTT FINNILA |
| ELECTRICAL-Final | 2/1/2022 | Corrections Issued | JOSE AVILA |
| Green Building Final | 2/1/2022 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 2/1/2022 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 2/1/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 2/11/2022 | Approved | JOSE AVILA |
| Green Building Final | 2/11/2022 | Approved | JOSE AVILA |
| Smoke Detectors | 2/11/2022 | Approved | JOSE AVILA |
| HVAC-Final | 2/23/2022 | Approved | JOSE AVILA |
| PLUMBING-Final | 3/9/2022 | Approved | JOSE AVILA |
| Final | 3/14/2022 | Corrections Issued | JOSE AVILA |
| Final | 3/21/2022 | OK to Issue CofO | JOSE AVILA |