17128 W VALERIO ST 91406

Certificate Information: 17128 W VALERIO ST 91406

Application / Permit
21016-20000-04840
Plan Check / Job No.
B21VN02211
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE INTO A (N) ACCESSORY DWELLING UNIT. (17'-4"x18'-9") per LAMC 12.22 A.33(c)¹, (d)¹, and (g), ALL WORK PER WFPP
Permit Issued
Issued on 7/21/2021
Issuing Office
Current Status
CofO Issued on 8/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/24/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 MOHAMMAD ESMAILI
Corrections Issued 3/6/2021 MOHAMMAD ESMAILI
Plan Check Approved 7/21/2021 MOHAMMAD ESMAILI
Issued 7/21/2021 APPLICANT
CofO in Progress 8/18/2022 RAUL OLAGI
Permit Finaled 8/27/2022 DEROLD HAUFF
CofO Issued 8/27/2022 DEROLD HAUFF
Permit Finaled 8/27/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/15/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 5/18/2021 GABRIEL ROBLES
Construction within easement Cleared 6/19/2021 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/24/2021 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 8/26/2021 Approved MICHEL ABAJAN
Green Building Rough 11/8/2021 Approved RAUL OLAGI
Insulation 11/8/2021 Approved RAUL OLAGI
Wood Frame 11/8/2021 Approved RAUL OLAGI
Drywall Nailing 11/17/2021 Approved ALAN MORELOS
Final 2/2/2022 Corrections Issued RAUL OLAGI
Green Building Final 2/2/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 2/2/2022 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 2/2/2022 Corrections Issued RAUL OLAGI
Final 2/10/2022 Corrections Issued RAUL OLAGI
Green Building Final 2/10/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 2/10/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 2/10/2022 Approved RAUL OLAGI
Final 2/17/2022 Not Ready for Inspection RAUL OLAGI
Green Building Final 2/17/2022 Approved RAUL OLAGI
Final 8/5/2022 Corrections Issued RAUL OLAGI
Final 8/17/2022 OK to Issue CofO RAUL OLAGI