5531 W RED OAK DR 90068
Certificate Information: 5531 W RED OAK DR 90068
- Application / Permit
- 21016-20000-04825
- Plan Check / Job No.
- B21VN02199
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL KITCHEN, BATHROOMS, FAMILY ROOM, DINING ROOM, BEDROOMS OF (E) 2-STORY SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/6/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/21/2022
Permit Application Status History
| Submitted | 2/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2021 | RAPHAEL ROSAS |
| Corrections Issued | 3/13/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 4/27/2021 | RAPHAEL ROSAS |
| Issued | 5/6/2021 | APPLICANT |
| Building Plans Picked Up | 5/10/2021 | APPLICANT |
| Permit Finaled | 4/21/2022 | ALIZAH MAYAGOITIA |
Permit Application Clearance Information
| "D" conditions | Cleared | 3/25/2021 | LIKYELESH ABERA |
| Grading Pre-Inspection | Cleared | 4/20/2021 | PATRICK MISCHLICH |
Contact Information
| Contractor | Mod Design Build; Lic. No.: 1031321-B | PO BOX 65008 LOS ANGELES, CA 90065 |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/12/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 5/17/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/10/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 6/10/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 6/10/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 6/10/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 6/17/2021 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 6/17/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 6/17/2021 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 6/17/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 6/24/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 7/12/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 7/12/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Shower Pan | 7/12/2021 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 7/14/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 7/27/2021 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 3/18/2022 | SGSOV Not Ready | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/7/2022 | SGSOV Not Ready | BRIAN SULLIVAN |
| ELECTRICAL-Final | 4/8/2022 | Approved | RUBEN SALAS |
| Grading Pre-Inspection | 4/8/2022 | Approved | RUBEN SALAS |
| HVAC-Final | 4/8/2022 | Corrections Issued | RUBEN SALAS |
| PLUMBING-Final | 4/8/2022 | Approved | RUBEN SALAS |
| ELECTRICAL-Final | 4/21/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/21/2022 | Permit Finaled | ALIZAH MAYAGOITIA |
| HVAC-Final | 4/21/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 4/21/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/21/2022 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/21/2022 | Approved | ALIZAH MAYAGOITIA |