5531 W RED OAK DR 90068

Certificate Information: 5531 W RED OAK DR 90068

Application / Permit
21016-20000-04825
Plan Check / Job No.
B21VN02199
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL KITCHEN, BATHROOMS, FAMILY ROOM, DINING ROOM, BEDROOMS OF (E) 2-STORY SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/6/2021
Issuing Office
Current Status
Permit Finaled on 4/21/2022

Permit Application Status History

Submitted 2/24/2021 APPLICANT
Assigned to Plan Check Engineer 3/10/2021 RAPHAEL ROSAS
Corrections Issued 3/13/2021 RAPHAEL ROSAS
Plan Check Approved 4/27/2021 RAPHAEL ROSAS
Issued 5/6/2021 APPLICANT
Building Plans Picked Up 5/10/2021 APPLICANT
Permit Finaled 4/21/2022 ALIZAH MAYAGOITIA

Permit Application Clearance Information

"D" conditions Cleared 3/25/2021 LIKYELESH ABERA
Grading Pre-Inspection Cleared 4/20/2021 PATRICK MISCHLICH

Contact Information

Contractor Mod Design Build; Lic. No.: 1031321-B PO BOX 65008      LOS ANGELES, CA 90065
Engineer Basso,, Alexandre; Lic. No.: C77670 7231 SUMMITROSE ST      TUJUNGA, CA 91042

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/12/2021 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 5/17/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 6/10/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 6/10/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 6/10/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 6/10/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 6/17/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 6/17/2021 Approved BRIAN SULLIVAN
HVAC-Rough 6/17/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 6/17/2021 Approved BRIAN SULLIVAN
Insulation 6/24/2021 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 7/12/2021 Not Ready for Inspection JUSTIN HAWLEY
Interior/Exterior Lathing 7/12/2021 Not Ready for Inspection JUSTIN HAWLEY
Shower Pan 7/12/2021 Approved JUSTIN HAWLEY
Drywall Nailing 7/14/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 7/27/2021 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/18/2022 SGSOV Not Ready BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 4/7/2022 SGSOV Not Ready BRIAN SULLIVAN
ELECTRICAL-Final 4/8/2022 Approved RUBEN SALAS
Grading Pre-Inspection 4/8/2022 Approved RUBEN SALAS
HVAC-Final 4/8/2022 Corrections Issued RUBEN SALAS
PLUMBING-Final 4/8/2022 Approved RUBEN SALAS
ELECTRICAL-Final 4/21/2022 Approved ALIZAH MAYAGOITIA
Final 4/21/2022 Permit Finaled ALIZAH MAYAGOITIA
HVAC-Final 4/21/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 4/21/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 4/21/2022 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 4/21/2022 Approved ALIZAH MAYAGOITIA