16762-16764 W ROMAR ST 91343

Certificate Information: 16762-16764 W ROMAR ST 91343

Application / Permit
21016-20000-04770
Plan Check / Job No.
B21VN02180
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT THE (E) 21' X 20' ATTACHED GARAGE TO (E) SFD AND 8' X 5'9-1/2" LAUNDRY INTO ACCESORY DWELLING UNIT AS PER GCS 65852.2(E)(1)(A), ALL WORK PER WFPP
Permit Issued
Issued on 4/8/2021
Issuing Office
Current Status
CofO Issued on 12/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 RARES BODEA
Corrections Issued 3/6/2021 RARES BODEA
Issued 4/8/2021 APPLICANT
Building Plans Picked Up 4/14/2021 APPLICANT
CofO in Progress 9/14/2021 MARK JOHNSON
Permit Finaled 12/11/2021 MICHAEL SMITH
CofO Issued 12/11/2021 MICHAEL SMITH
Permit Finaled 12/11/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/16/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/16/2021 ADRIAN CASTRO
Sewer availability Cleared 3/16/2021 ADRIAN CASTRO
Watercourse Cleared 3/16/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/14/2021 Partial Approval MISAEL ESPARZA
Sewer 4/14/2021 Approved MISAEL ESPARZA
Footing/Foundation/Slab 4/22/2021 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 5/5/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 5/24/2021 Approved MARK JOHNSON
PLUMBING-Rough 5/24/2021 Corrections Issued MARK JOHNSON
BUILDING-Rough-Frame 6/9/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 6/9/2021 Approved MARK JOHNSON
PLUMBING-Rough 6/9/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 6/22/2021 Approved MARK JOHNSON
Green Building Rough 6/22/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 6/25/2021 Approved ARTHUR SARGSYAN
Shower Pan 6/25/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 7/2/2021 Approved MORRIS JACKSON
Insulation 7/2/2021 Approved MORRIS JACKSON
Final 8/16/2021 Not Ready for Inspection MARK JOHNSON
Green Building Final 8/16/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 8/16/2021 SGSOV Approved MARK JOHNSON
Service/Power Release 8/16/2021 Not Required MARK JOHNSON
Smoke Detectors 8/16/2021 Approved MARK JOHNSON
Final 8/20/2021 Corrections Issued MARK JOHNSON
Final 9/1/2021 Corrections Issued MARK JOHNSON
Pre-Inspection 9/8/2021 Partial Inspection MARK JOHNSON
Final 9/13/2021 OK to Issue CofO MARK JOHNSON