15946-15948 W ECCLES ST 91343

Certificate Information: 15946-15948 W ECCLES ST 91343

Application / Permit
21016-20000-04721
Plan Check / Job No.
B21VN02160
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (364 SQ FT) PER LAMC 12.22 A. 33(c) and (e)  
Permit Issued
Issued on 5/5/2021
Issuing Office
Current Status
CofO Issued on 2/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2021 APPLICANT
Assigned to Plan Check Engineer 3/9/2021 JEROME MAGAT PALMA
Corrections Issued 3/9/2021 JEROME MAGAT PALMA
Plan Check Approved 4/25/2021 JEROME MAGAT PALMA
Issued 5/5/2021 APPLICANT
Building Plans Picked Up 5/20/2021 APPLICANT
CofO in Progress 1/28/2022 RAUL OLAGI
Permit Finaled 2/12/2022 MICHAEL SMITH
CofO Issued 2/12/2022 MICHAEL SMITH
Permit Finaled 2/12/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/7/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/7/2021 ADRIAN CASTRO
Sewer availability Cleared 4/7/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/31/2021 Partial Inspection JENNIFER RABUCHIN
Sewer 8/31/2021 Not Ready for Inspection JENNIFER RABUCHIN
Deputy Drilled-In Anchors 9/1/2021 Approved JACK KARGODORIAN
Footing/Foundation/Slab 9/3/2021 Approved JACK KARGODORIAN
Sewer 9/3/2021 Approved JACK KARGODORIAN
Deputy Drilled-In Anchors 9/9/2021 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 9/10/2021 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 9/10/2021 Approved JACK KARGODORIAN
PLUMBING-Rough 9/10/2021 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 9/10/2021 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 9/29/2021 Corrections Issued JACK KARGODORIAN
HVAC-Rough 9/29/2021 Approved JACK KARGODORIAN
PLUMBING-Rough 9/29/2021 Approved JACK KARGODORIAN
ELECTRICAL-Rough 10/1/2021 Approved JACK KARGODORIAN
PLUMBING-Rough 10/1/2021 Approved JACK KARGODORIAN
Insulation 10/12/2021 Approved JACK KARGODORIAN
Drywall Nailing 10/18/2021 Approved ALAN MORELOS
Drywall Nailing 10/25/2021 Corrections Issued ALAN MORELOS
Special/Order Compliance 10/25/2021 Partial Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 10/27/2021 Approved RAUL OLAGI
BUILDING-Rough-Frame 1/12/2022 Approved RAUL OLAGI
Final 1/12/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 1/12/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 1/12/2022 Approved RAUL OLAGI
Final 1/27/2022 OK to Issue CofO RAUL OLAGI