6512 1/2 W LINDENHURST AVE 90048

Certificate Information: 6512 1/2 W LINDENHURST AVE 90048

Application / Permit
21016-20000-04700
Plan Check / Job No.
B21VN02154
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 17'2" X 20'3" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT AS PER GCS 65852(E)(1)(A), ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/3/2021
Issuing Office
Current Status
CofO Issued on 6/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 RARES BODEA
Corrections Issued 3/7/2021 RARES BODEA
Plan Check Approved 4/16/2021 RARES BODEA
Plan Check Approved 4/26/2021 RARES BODEA
Building Plans Picked Up 4/27/2021 APPLICANT
Issued 11/3/2021 APPLICANT
Permit Finaled 6/7/2025 RICHARD STEINBACH
CofO Issued 6/7/2025 RICHARD STEINBACH
Permit Finaled 6/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

ZI Cleared 3/23/2021 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 3/24/2021 JEANIE LAM
Sewer availability Cleared 3/24/2021 JEANIE LAM
Address approval Cleared 3/30/2021 JEANIE LAM
Construction near power lines Cleared 4/1/2021 WALTER RAMIREZ
Construction within easement Cleared 4/1/2021 WALTER RAMIREZ

Contact Information

Contractor Concept Renovations Inc; Lic. No.: 1016942-B 15928 VENTURA BLVD 225      ENCINO, CA 91436
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 8916 LONGDON AVE #C      TEMPLE CITY, CA 91780

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/27/2022 Approved EVAN COOPER
PLUMBING-Rough 1/27/2022 Partial Approval EVAN COOPER
Underground Mechanical 1/27/2022 Approved EVAN COOPER
Deputy Wood Construction 2/9/2022 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 2/18/2022 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 2/18/2022 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 3/1/2022 Approved EVAN COOPER
ELECTRICAL-Rough 3/1/2022 Approved EVAN COOPER
Green Building Rough 3/1/2022 Approved EVAN COOPER
HVAC-Rough 3/1/2022 Approved EVAN COOPER
Interior/Exterior Lathing 3/1/2022 Approved EVAN COOPER
METHANE-Rough 3/1/2022 Approved EVAN COOPER
PLUMBING-Rough 3/1/2022 Approved EVAN COOPER
ELECTRICAL-Rough 3/10/2022 Approved EVAN COOPER
Green Building Rough 3/10/2022 Approved EVAN COOPER
Insulation 3/10/2022 Approved EVAN COOPER
Interior/Exterior Lathing 3/10/2022 Approved EVAN COOPER
PLUMBING-Rough 3/10/2022 Approved EVAN COOPER
Shower Pan 3/10/2022 Approved EVAN COOPER
Drywall Nailing 3/21/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 4/28/2022 SGSOV Approved EVAN COOPER
Service/Power Release 4/28/2022 Approved EVAN COOPER
Smoke Detectors 4/28/2022 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Final 6/21/2022 Approved EVAN COOPER
Final 6/21/2022 Conditional Approval EVAN COOPER
HVAC-Final 6/21/2022 Approved EVAN COOPER
PLUMBING-Final 6/21/2022 Approved EVAN COOPER
Smoke Detectors 6/21/2022 Approved EVAN COOPER