17101 W STRAWBERRY DR 91436

Certificate Information: 17101 W STRAWBERRY DR 91436

Application / Permit
21016-20000-04585
Plan Check / Job No.
B21VN02100
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) KITCHEN, BATHROOMS, ADD NEW TRIM TO (E) POSTS AND REMODEL THROUGHOUT (E) 1-STORY SFD PER ENGINEERING.
Permit Issued
Issued on 4/5/2021
Issuing Office
Current Status
Permit Finaled on 2/6/2022

Permit Application Status History

Submitted 2/22/2021 APPLICANT
Assigned to Plan Check Engineer 3/9/2021 JENNIFER LEE
Corrections Issued 3/11/2021 JENNIFER LEE
Plan Check Approved 4/1/2021 JENNIFER LEE
Issued 4/5/2021 APPLICANT
Building Plans Picked Up 4/5/2021 APPLICANT
Permit Finaled 2/4/2022 VINCENT HANLEY

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/15/2021 JENNIFER LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Niver,, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

HVAC-Rough 4/16/2021 Approved RONALD COWAN
PLUMBING-Rough 4/16/2021 Partial Approval RONALD COWAN
ELECTRICAL-Rough 4/22/2021 Not Ready for Inspection RONALD COWAN
Footing/Foundation/Slab 4/26/2021 Not Ready for Inspection RONALD COWAN
HVAC-Rough 4/26/2021 Approved RONALD COWAN
Deputy Drilled-In Anchors 5/6/2021 Conditional Approval RYAN SALAZAR
Footing/Foundation/Slab 5/7/2021 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 5/13/2021 Corrections Issued RONALD COWAN
Excavation/Setback/Form/Re-Bar 5/14/2021 Approved MICHAEL PELHAM
Footing/Foundation/Slab 5/14/2021 Approved MICHAEL PELHAM
BUILDING-Rough-Frame 5/25/2021 Approved RONALD COWAN
ELECTRICAL-Rough 5/25/2021 Approved RONALD COWAN
HVAC-Rough 5/25/2021 Approved RONALD COWAN
Interior/Exterior Lathing 6/23/2021 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 7/2/2021 Approved DAVID SANDOVAL
Green Building Rough 7/2/2021 Approved DAVID SANDOVAL
Interior/Exterior Lathing 7/2/2021 Partial Approval DAVID SANDOVAL
Insulation 7/20/2021 Approved RONALD COWAN
Shower Pan 7/20/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 7/27/2021 Approved DAVID SANDOVAL
Drywall Nailing 7/28/2021 Partial Approval RYAN SALAZAR
Interior/Exterior Lathing 8/26/2021 Approved KRISTEN CAUSEY
Pre-Inspection 1/25/2022 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Final 2/4/2022 Approved VINCENT HANLEY
Final 2/4/2022 Permit Finaled VINCENT HANLEY
HVAC-Final 2/4/2022 Approved VINCENT HANLEY
PLUMBING-Final 2/4/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 2/4/2022 SGSOV Approved VINCENT HANLEY
Smoke Detectors 2/4/2022 Approved VINCENT HANLEY