4645-4647 N BURNET AVE 91403

Certificate Information: 4645-4647 N BURNET AVE 91403

Application / Permit
21016-20000-04533
Plan Check / Job No.
B21VN02071
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO (21'-8" x 18'-4") NEW ADU PER CA GOVT. CODE 65852.2 (e)(1)(A)
Permit Issued
Issued on 9/3/2021
Issuing Office
Current Status
CofO Issued on 8/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/22/2021 APPLICANT
Assigned to Plan Check Engineer 3/11/2021 PETER MOSESIAN
Corrections Issued 3/12/2021 PETER MOSESIAN
Quality Review Completed 3/30/2021 OMID HEDAYAT
Plan Check Approved 8/17/2021 PETER MOSESIAN
Issued 9/3/2021 APPLICANT
CofO in Progress 8/12/2022 JACK KARGODORIAN
Permit Finaled 8/13/2022 DEROLD HAUFF
CofO Issued 8/13/2022 DEROLD HAUFF
Permit Finaled 8/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/8/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 4/26/2021 GABRIEL ROBLES
Sewer availability Cleared 4/26/2021 GABRIEL ROBLES
Construction near power lines Cleared 5/11/2021 WALTER RAMIREZ
Low Impact Development Cleared 7/22/2021 SUNG JOON WON

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/16/2021 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 11/24/2021 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 2/11/2022 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 2/14/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 4/12/2022 Partial Approval JACK KARGODORIAN
Drywall Nailing 6/16/2022 Approved JACK KARGODORIAN
Final 6/16/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 6/16/2022 Approved JACK KARGODORIAN
Green Building Rough 6/16/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/16/2022 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 6/16/2022 Approved JACK KARGODORIAN
Wood Frame 6/16/2022 Approved JACK KARGODORIAN
Final 6/28/2022 Partial Inspection HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 6/28/2022 SGSOV Approved HERBERT GIRON
Final 8/12/2022 OK to Issue CofO JACK KARGODORIAN