11645 W MCCORMICK ST 91601
Certificate Information: 11645 W MCCORMICK ST 91601
- Application / Permit
- 21016-20000-04518
- Plan Check / Job No.
- B21VN02054
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-3" x 20'-2" GARAGE TO ACCESSORRY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A); AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 5/13/2021
- Issuing Office
- Current Status
- CofO Issued on 10/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | SEAN SHAHMIRI |
| Corrections Issued | 3/22/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 3/30/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/12/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 5/12/2021 | SEAN SHAHMIRI |
| Issued | 5/13/2021 | APPLICANT |
| CofO in Progress | 5/30/2023 | JOHN COLEMAN |
| CofO Issued | 10/23/2023 | RUBEN SALAS |
| Permit Finaled | 10/23/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/18/2021 | GUILLERMO PETRA |
| Specific Plan | Cleared | 4/20/2021 | CORREY KITCHENS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/30/2021 | Partial Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/10/2021 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/21/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 9/23/2021 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 10/5/2021 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2021 | Partial Inspection | THOMAS FINNILA |
| Pre-Inspection | 12/3/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 12/6/2021 | Approved | THOMAS FINNILA |
| HVAC-Rough | 12/6/2021 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 12/6/2021 | Approved | THOMAS FINNILA |
| HVAC-Rough | 12/28/2021 | Approved | THOMAS FINNILA |
| Wood Frame | 12/28/2021 | Corrections Issued | THOMAS FINNILA |
| Pre-Inspection | 1/3/2022 | Conditional Approval | THOMAS FINNILA |
| Insulation | 1/21/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 2/10/2022 | Conditional Approval | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 5/9/2022 | Partial Approval | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/8/2022 | SGSOV Not Ready | MATT KELLERMAN |
| BUILDING-Rough-Frame | 7/14/2022 | Approved | THOMAS FINNILA |
| Final | 7/14/2022 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 7/14/2022 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 7/14/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/14/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Final | 5/15/2023 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 5/15/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 5/15/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 5/15/2023 | Approved | JACK KARGODORIAN |
| Final | 5/25/2023 | OK to Issue CofO | JOHN COLEMAN |
| Underground Mechanical | 5/31/2023 | Corrections Issued | JOHN COLEMAN |
| Pre-Inspection | 8/14/2023 | Approved | JACK KARGODORIAN |