6509-6511 N PLATT AVE 91307

Certificate Information: 6509-6511 N PLATT AVE 91307

Application / Permit
21016-20000-04474
Plan Check / Job No.
B21VN02031
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) ATTACHED 2- CAR GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2 (e)(1)(A). WORK PER LA STD WFPP.
Permit Issued
Issued on 4/13/2021
Issuing Office
Current Status
CofO Issued on 12/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 TROY DEGUZMAN
Corrections Issued 3/6/2021 TROY DEGUZMAN
Building Plans Picked Up 3/16/2021 APPLICANT
Plan Check Approved 4/13/2021 TROY DEGUZMAN
Issued 4/13/2021 APPLICANT
CofO in Progress 12/21/2021 TROY SANDERS
CofO Issued 12/22/2021 JOHN JANSON
Permit Finaled 12/22/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/19/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/19/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/19/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 9/7/2021 Approved PETER FOLLING
Gas Test 9/7/2021 Not Ready for Inspection PETER FOLLING
Insulation 9/7/2021 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 9/7/2021 Not Ready for Inspection PETER FOLLING
Sewer 9/7/2021 Not Ready for Inspection PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 9/13/2021 Not Ready for Inspection TROY SANDERS
HVAC-Rough 9/13/2021 Approved TROY SANDERS
Insulation 9/13/2021 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 9/13/2021 Approved TROY SANDERS
Sewer 9/13/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 9/17/2021 Approved TROY SANDERS
Green Building Rough 9/17/2021 Approved TROY SANDERS
Insulation 9/17/2021 Approved TROY SANDERS
Interior/Exterior Lathing 9/17/2021 Partial Approval TROY SANDERS
Shower Pan 9/17/2021 Not Ready for Inspection TROY SANDERS
Drywall Nailing 9/30/2021 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 9/30/2021 Approved STEPHANIE SWANSON
Shower Pan 9/30/2021 Approved STEPHANIE SWANSON
Final 12/3/2021 Corrections Issued TROY SANDERS
Green Building Final 12/3/2021 Corrections Issued TROY SANDERS
SGSOV-Seismic Gas S/O Valve 12/3/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 12/3/2021 Approved TROY SANDERS
Final 12/21/2021 OK to Issue CofO TROY SANDERS
Green Building Final 12/21/2021 Approved TROY SANDERS