17259 W DEVONSHIRE ST 91325

Certificate Information: 17259 W DEVONSHIRE ST 91325

Application / Permit
21016-20000-04442
Plan Check / Job No.
B21VN02001
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE (E) TRELLIS (15'-10" X 9'-6") TO EXPAND ENTRY TO (E) SFD W/ ATTACHED GARAGE PER ENG'R DESIGN
Permit Issued
Issued on 3/23/2021
Issuing Office
Current Status
CofO Issued on 9/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 NILOOFAR MEHRAIN
Corrections Issued 3/6/2021 NILOOFAR MEHRAIN
Plan Check Approved 3/23/2021 OMAR GARNICA
Issued 3/23/2021 APPLICANT
Building Plans Picked Up 3/24/2021 APPLICANT
Permit Finaled 9/20/2025 MICHAEL PELHAM
CofO Issued 9/20/2025 MICHAEL PELHAM
Permit Finaled 9/20/2025 MICHAEL PELHAM

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/12/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 3/12/2021 ADRIAN CASTRO

Contact Information

Contractor Topaz Remodeling Inc; Lic. No.: 1019003-B 5789 FAIRHAVEN AVE      WOODLAND HILLS, CA 91367
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/31/2021 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 4/8/2021 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 4/19/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 4/23/2021 Approved JEFFREY PARD
HVAC-Rough 4/23/2021 Approved JEFFREY PARD
BUILDING-Rough-Frame 4/29/2021 Approved JEFFREY PARD
Green Building Rough 4/29/2021 Approved JEFFREY PARD
Insulation 4/29/2021 Approved JEFFREY PARD
Interior/Exterior Lathing 4/29/2021 Approved JEFFREY PARD
Drywall Nailing 5/5/2021 Approved RYAN SALAZAR
Final 11/15/2021 Partial Approval JEFFREY PARD
Green Building Final 11/15/2021 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 11/15/2021 SGSOV Approved JEFFREY PARD
Smoke Detectors 11/15/2021 Approved JEFFREY PARD