3803 S BUCKINGHAM ROAD 90008
Certificate Information: 3803 S BUCKINGHAM ROAD 90008
- Application / Permit
- 21016-20000-04382
- Plan Check / Job No.
- B21VN01974
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 4'-9" X 15'-7"ADDITION TO AND CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT. PER LAMC 12.22 A.33 (c) AND (d).
- Permit Issued
- Issued on 3/29/2022
- Issuing Office
- Current Status
- CofO Issued on 7/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 6/10/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 2/2/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 3/24/2022 | LUISANGEL VALENZUELA |
| Issued | 3/29/2022 | APPLICANT |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| CofO in Progress | 6/27/2023 | ANTHONY EGSON |
| Permit Finaled | 7/8/2023 | DEROLD HAUFF |
| CofO Issued | 7/8/2023 | DEROLD HAUFF |
| Permit Finaled | 7/8/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/13/2021 | RIDWAN HARDY |
| Address approval | Cleared | 9/25/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/29/2021 | CECILIO NAVARRO |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | So Cal Builders And Design Inc; Lic. No.: 990258-B | 15335 MORRISON STREET #375 SHERMAN OAKS, CA 91403 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/19/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/27/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/21/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/24/2022 | Not Ready for Inspection | HORACE FULTZ |
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | No Access for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 6/30/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/5/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 7/25/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 7/25/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/1/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 8/1/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 8/1/2022 | Approved | ANTHONY EGSON |
| Wood Frame | 8/9/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/17/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 8/17/2022 | Approved | ANTHONY EGSON |
| Insulation | 8/25/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/25/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/31/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 9/6/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Sewer | 9/21/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/8/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 11/16/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 3/7/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 3/7/2023 | Approved | ANTHONY EGSON |
| Final | 3/7/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 3/7/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 3/7/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Not Ready | ANTHONY EGSON |
| Service/Power Release | 3/7/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 3/7/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 5/1/2023 | Approved | ANTHONY EGSON |
| Final | 5/1/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 5/1/2023 | Approved | ANTHONY EGSON |
| HVAC-Final | 5/1/2023 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 5/1/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 5/1/2023 | SGSOV Approved | ANTHONY EGSON |
| Final | 5/31/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 6/27/2023 | OK to Issue CofO | ANTHONY EGSON |