20531 W MIRANDA PL 91367

Certificate Information: 20531 W MIRANDA PL 91367

Application / Permit
21016-20000-04373
Plan Check / Job No.
B21VN01971
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Carport
Work Description
CONVERT THE (E)ATTACHED GARAGE INTO A MASTER BEDROOM, INTERIOR REMODEL AND ADD 18'-0" x 18'-2" ATTACHED CARPORT PER P/BC 2017-005 TO THE (E)SINGLE FAMILY DWELLING. ALL WORK PER WFPP.
Permit Issued
Issued on 5/20/2021
Issuing Office
Current Status
Issued on 5/20/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/19/2021 APPLICANT
Assigned to Plan Check Engineer 3/8/2021 DAVID CASTILLO
Corrections Issued 3/15/2021 DAVID CASTILLO
Applicant returned to address corrections 4/6/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 4/14/2021 DAVID CASTILLO
Applicant returned to address corrections 4/22/2021 ALFREDO JARA
Applicant returned to address corrections 5/6/2021 SARKIS HARABEDIAN
Plan Check Approved 5/14/2021 SARKIS HARABEDIAN
Issued 5/20/2021 APPLICANT
Building Plans Picked Up 5/21/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/1/2021 ADRIAN CASTRO
Sewer availability Cleared 4/1/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 5/11/2021 GABRIEL ROBLES
Grading Pre-Inspection Cleared 5/14/2021 DAVID CASTILLO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 5/6/2025   
Smoke Detectors 5/6/2025   
Green Building Final 5/6/2025   

Inspection Request History

ELECTRICAL-Rough 6/25/2021 Not Ready for Inspection HENRY KIM
HVAC-Rough 6/25/2021 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 6/25/2021 Not Ready for Inspection HENRY KIM
Pre-Inspection 6/25/2021 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 7/2/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 7/2/2021 Not Ready for Inspection HENRY KIM
Green Building Rough 7/2/2021 Not Ready for Inspection HENRY KIM
HVAC-Rough 7/2/2021 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 7/2/2021 Corrections Issued HENRY KIM
ELECTRICAL-Rough 7/8/2021 Not Ready for Inspection HENRY KIM
HVAC-Rough 7/8/2021 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 7/8/2021 Partial Approval HENRY KIM
BUILDING-Rough-Frame 7/26/2021 Partial Approval HENRY KIM
ELECTRICAL-Rough 7/26/2021 Partial Approval HENRY KIM
Insulation 7/26/2021 Partial Approval HENRY KIM
PLUMBING-Rough 7/26/2021 Partial Approval HENRY KIM
Drywall Nailing 8/2/2021 Partial Approval HENRY KIM
Interior/Exterior Lathing 8/2/2021 Not Ready for Inspection HENRY KIM
Shower Pan 8/2/2021 Corrections Issued HENRY KIM
Green Building Rough 8/4/2021 Partial Approval CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 8/4/2021 Approved CHRISTOPHER DELLEFIELD
Shower Pan 8/4/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Shower Pan 8/6/2021 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 1/18/2023 Approved ALEXANDER HANDY
Drywall Nailing 1/18/2023 Approved ALEXANDER HANDY
Final 1/18/2023 Corrections Issued ALEXANDER HANDY
Footing/Foundation/Slab 1/18/2023 Approved ALEXANDER HANDY
Green Building Final 1/18/2023 Not Ready for Inspection ALEXANDER HANDY
Green Building Rough 1/18/2023 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 1/18/2023 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 1/18/2023 Not Ready for Inspection ALEXANDER HANDY
Wood Frame 6/5/2024 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 8/5/2024 Not Ready for Inspection ARUTYUN MADATYAN
HVAC-Rough 8/5/2024 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Rough 8/5/2024 Not Ready for Inspection ARUTYUN MADATYAN
Wood Frame 8/5/2024 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 9/4/2024 Approved ALEXANDER HANDY
HVAC-Rough 9/4/2024 Approved ALEXANDER HANDY
PLUMBING-Rough 9/4/2024 Corrections Issued ALEXANDER HANDY
Structural Steel Frame 9/4/2024 Not Ready for Inspection ALEXANDER HANDY
Wood Frame 9/4/2024 Partial Approval ALEXANDER HANDY
Special/Order Compliance 9/5/2024 Corrections Issued ALEXANDER HANDY
Insulation 10/3/2024 Not Ready for Inspection ALEXANDER HANDY
Interior/Exterior Lathing 10/3/2024 Not Ready for Inspection ALEXANDER HANDY
Shower Pan 10/3/2024 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 11/14/2024 Approved ALEXANDER HANDY
Drywall Nailing 11/14/2024 Approved ALEXANDER HANDY
ELECTRICAL-Rough 11/14/2024 Approved ALEXANDER HANDY
Green Building Rough 11/14/2024 Approved ALEXANDER HANDY
HVAC-Rough 11/14/2024 Approved ALEXANDER HANDY
Interior/Exterior Lathing 11/14/2024 Approved ALEXANDER HANDY
PLUMBING-Rough 11/14/2024 Approved ALEXANDER HANDY