1145 S FRESNO ST 90023

Certificate Information: 1145 S FRESNO ST 90023

Application / Permit
21016-20000-04218
Plan Check / Job No.
B21VN01903
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 1-STORY 18' x 20' ATT. GARAGE (330 SF) OF (E) SFD INTO FAMILY ROOM AND BEDROOM AND PROVIDE NEW ATTACHED 1 CAR CARPORT. WORK PER ENGINEERING.
Permit Issued
Issued on 3/23/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2021 APPLICANT
Assigned to Plan Check Engineer 3/8/2021 REZA HAGHIGHAT
Corrections Issued 3/15/2021 REZA HAGHIGHAT
Applicant returned to address corrections 6/24/2022 MOHAMMAD ESMAILI
Building Plans Picked Up 6/27/2022 APPLICANT
Plan Check Approved 1/12/2023 ISIS ARGUETA
Issued 3/23/2023 APPLICANT
CofO in Progress 9/7/2025 FREDDIE RIVERA
CofO Issued 9/8/2025 DEROLD HAUFF
Permit Finaled 9/8/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/14/2021 STEVE MELGAR
Sewer availability Cleared 7/14/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 3/29/2022 STEVE MELGAR
Hydrant and Access approval Cleared 4/26/2022 MATTHEW CRAIG
Address approval Cleared 6/24/2022 STEVE MELGAR
Low Impact Development Cleared 12/21/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 1/3/2023 STEVE MELGAR
Grading Pre-Inspection Cleared 1/12/2023 REZA HAGHIGHAT

Contact Information

Contractor Norsar Construction Inc; Lic. No.: 942423-B 15940 KALISHER STREET      GRANADA HILLS, CA 91344
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 2/22/2024 Approved FREDDIE RIVERA
PLUMBING-Rough 2/22/2024 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Partial Approval FREDDIE RIVERA
HVAC-Rough 3/19/2024 Partial Inspection FREDDIE RIVERA
MERV13>=Rough 3/19/2024 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 4/4/2024 Conditional Approval FREDDIE RIVERA
Green Building Rough 4/4/2024 Approved FREDDIE RIVERA
HVAC-Rough 4/4/2024 Approved FREDDIE RIVERA
Insulation 4/4/2024 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 4/25/2024 Approved FREDDIE RIVERA
MERV13>=Rough 4/25/2024 Approved FREDDIE RIVERA
Drywall Nailing 2/14/2025 Not Ready for Inspection FREDDIE RIVERA
Final 2/14/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 2/14/2025 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 2/14/2025 Not Ready for Inspection FREDDIE RIVERA
MERV13>=Final 2/14/2025 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/14/2025 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 2/14/2025 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 5/30/2025 Partial Inspection FREDDIE RIVERA
Drywall Nailing 7/11/2025 Partial Inspection FREDDIE RIVERA
Final 7/11/2025 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 7/11/2025 Partial Inspection FREDDIE RIVERA
Green Building Final 7/11/2025 Partial Inspection FREDDIE RIVERA
MERV13>=Final 7/11/2025 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/11/2025 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 7/11/2025 Partial Inspection FREDDIE RIVERA
Drywall Nailing 9/8/2025 Approved FREDDIE RIVERA
Final 9/8/2025 OK to Issue CofO FREDDIE RIVERA
Footing/Foundation/Slab 9/8/2025 Approved FREDDIE RIVERA
Green Building Final 9/8/2025 Approved FREDDIE RIVERA
MERV13>=Final 9/8/2025 Approved FREDDIE RIVERA
Smoke Detectors 9/8/2025 Approved FREDDIE RIVERA