6580 N SHELTONDALE AVE 91307

Certificate Information: 6580 N SHELTONDALE AVE 91307

Application / Permit
21016-20000-03912
Plan Check / Job No.
B21VN01764
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20'x20' REC. ROOM INTO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 7/2/2021
Issuing Office
Current Status
CofO Corrected on 12/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/25/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 SEAN SHAHMIRI
Corrections Issued 3/6/2021 SEAN SHAHMIRI
Building Plans Picked Up 3/10/2021 APPLICANT
Applicant returned to address corrections 4/19/2021 SEAN SHAHMIRI
Applicant returned to address corrections 6/30/2021 SEAN SHAHMIRI
Plan Check Approved 7/2/2021 SEAN SHAHMIRI
Issued 7/2/2021 APPLICANT
CofO in Progress 10/14/2021 TROY SANDERS
CofO Issued-Status Void 10/15/2021 MICHAEL SMITH
Permit Finaled-Status Void 10/15/2021 MICHAEL SMITH
Re-Activate Permit 12/3/2021 JOHN JANSON
Permit Finaled 12/3/2021 JOHN JANSON
CofO Corrected 12/3/2021 JOHN JANSON
Permit Finaled 12/3/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/18/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/18/2021 ADRIAN CASTRO
Construction within easement Cleared 6/10/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/13/2021 No Access for Inspection TROY SANDERS
ELECTRICAL-Rough 7/13/2021 No Access for Inspection TROY SANDERS
PLUMBING-Rough 7/13/2021 No Access for Inspection TROY SANDERS
BUILDING-Rough-Frame 7/16/2021 Partial Approval TROY SANDERS
ELECTRICAL-Rough 7/16/2021 Partial Approval TROY SANDERS
Green Building Rough 7/16/2021 Not Ready for Inspection TROY SANDERS
Insulation 7/16/2021 Approved TROY SANDERS
PLUMBING-Rough 7/16/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 7/26/2021 Approved STEPHANIE SWANSON
Drywall Nailing 7/26/2021 Approved STEPHANIE SWANSON
ELECTRICAL-Final 7/26/2021 Corrections Issued STEPHANIE SWANSON
Green Building Rough 7/26/2021 Approved STEPHANIE SWANSON
HVAC-Rough 7/26/2021 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 7/26/2021 Partial Approval STEPHANIE SWANSON
PLUMBING-Final 7/26/2021 Partial Approval STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 7/26/2021 SGSOV Approved STEPHANIE SWANSON
ELECTRICAL-Final 8/26/2021 Approved TROY SANDERS
Final 8/26/2021 Not Ready for Inspection TROY SANDERS
Green Building Final 8/26/2021 Approved TROY SANDERS
HVAC-Final 8/26/2021 Approved TROY SANDERS
PLUMBING-Final 8/26/2021 Approved TROY SANDERS
Smoke Detectors 8/26/2021 Approved TROY SANDERS
Final 10/14/2021 OK to Issue CofO TROY SANDERS