7038-7040 N DARNOCH WAY 91307

Certificate Information: 7038-7040 N DARNOCH WAY 91307

Application / Permit
21016-20000-03621
Plan Check / Job No.
B21VN01689
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20'-7" X 23' ATTACHED GARAGETO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER DESIGN.
Permit Issued
Issued on 3/15/2021
Issuing Office
Current Status
CofO Issued on 12/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 2/24/2021 RAPHAEL ROSAS
Corrections Issued 2/25/2021 RAPHAEL ROSAS
Building Plans Picked Up 3/1/2021 APPLICANT
Plan Check Approved 3/15/2021 RAPHAEL ROSAS
Issued 3/15/2021 APPLICANT
CofO in Progress 12/22/2021 TROY SANDERS
CofO Issued 12/23/2021 JOHN JANSON
Permit Finaled 12/23/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/1/2021 ABDULLAH SADOZAI
Eng Process Fee Ord 176,300 Cleared 3/1/2021 ABDULLAH SADOZAI
Sewer availability Cleared 3/1/2021 ABDULLAH SADOZAI
ZA Case Cleared 3/1/2021 LAUREN PADICK
Grading Pre-Inspection Cleared 3/5/2021 BRIAN MILLER

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/21/2021 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 6/9/2021 Corrections Issued DAVID STEPANYAN
Deputy Drilled-In Anchors 6/16/2021 Conditional Approval DAVID STEPANYAN
Footing/Foundation/Slab 6/17/2021 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 6/17/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 7/1/2021 Not Ready for Inspection DAVID STEPANYAN
ELECTRICAL-Rough 7/1/2021 Partial Approval DAVID STEPANYAN
Green Building Rough 7/1/2021 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 8/9/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 8/9/2021 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 8/13/2021 Partial Approval DAVID STEPANYAN
Green Building Rough 8/13/2021 Corrections Issued DAVID STEPANYAN
Interior/Exterior Lathing 8/13/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 8/19/2021 Approved TROY SANDERS
Green Building Rough 8/19/2021 Approved TROY SANDERS
HVAC-Rough 8/19/2021 Approved TROY SANDERS
Insulation 8/19/2021 Approved TROY SANDERS
PLUMBING-Rough 8/19/2021 Approved TROY SANDERS
Drywall Nailing 8/31/2021 Approved HENRY KIM
ELECTRICAL-Final 8/31/2021 Corrections Issued HENRY KIM
Interior/Exterior Lathing 8/31/2021 Approved HENRY KIM
PLUMBING-Final 8/31/2021 Corrections Issued HENRY KIM
Shower Pan 8/31/2021 Approved HENRY KIM
Smoke Detectors 8/31/2021 Corrections Issued HENRY KIM
Final 12/1/2021 Corrections Issued TROY SANDERS
Green Building Final 12/1/2021 Corrections Issued TROY SANDERS
SGSOV-Seismic Gas S/O Valve 12/1/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 12/1/2021 Approved TROY SANDERS
Final 12/22/2021 OK to Issue CofO TROY SANDERS
Green Building Final 12/22/2021 Approved TROY SANDERS