917 S BUNDY DR 90049

Certificate Information: 917 S BUNDY DR 90049

Application / Permit
21016-20000-03575
Plan Check / Job No.
B21VN01664
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE THE WALL DIVIDING THE (E) GUEST HOUSE AND REC. ROOM ON TOP OF THE DETACHED GARAGE AND CONVERT THE GUEST HOUSE/REC. ROOM INTO A (N) ACCESSORY DWELLING UNIT, AND REMODEL PER GCS 65852.2(e)(1)(A). ALL WORK PER ENGINEERING. SEE COMMENT.
Permit Issued
Issued on 7/27/2021
Issuing Office
Current Status
CofO Issued on 10/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/11/2021 APPLICANT
Assigned to Plan Check Engineer 3/5/2021 PARISA ZAHABI
Corrections Issued 3/6/2021 PARISA ZAHABI
Applicant returned to address corrections 5/12/2021 PARISA ZAHABI
Plan Check Approved 5/27/2021 PARISA ZAHABI
Building Plans Picked Up 5/27/2021 APPLICANT
Issued 7/27/2021 APPLICANT
CofO in Progress 10/5/2022 RICHARD STEINBACH
Permit Finaled 10/6/2022 DANIEL ORRANTE
CofO Issued 10/6/2022 DANIEL ORRANTE
Permit Finaled 10/6/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/17/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 3/18/2021 DENNIS BRAGIN
Specific Plan Cleared 4/6/2021 KEVIN ARUCAN
Hydrant and Access approval Cleared 4/25/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Sayah,, Daniel Hoshyar; Lic. No.: S6000 15233 VENTURA BLVD 1130      SHERMAN OAKS, CA 91403

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Shower Pan 10/22/2021 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 4/5/2022 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/12/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/12/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 4/12/2022 Approved OGANES TARAKHCHYAN
Final 9/8/2022 No Access for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 9/8/2022 No Access for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/8/2022 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 9/8/2022 No Access for Inspection OGANES TARAKHCHYAN
Final 9/16/2022 Conditional Approval JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved JOHN KIDWELL
Smoke Detectors 9/16/2022 Approved JOHN KIDWELL