917 S BUNDY DR 90049
Certificate Information: 917 S BUNDY DR 90049
- Application / Permit
- 21016-20000-03575
- Plan Check / Job No.
- B21VN01664
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE THE WALL DIVIDING THE (E) GUEST HOUSE AND REC. ROOM ON TOP OF THE DETACHED GARAGE AND CONVERT THE GUEST HOUSE/REC. ROOM INTO A (N) ACCESSORY DWELLING UNIT, AND REMODEL PER GCS 65852.2(e)(1)(A). ALL WORK PER ENGINEERING. SEE COMMENT.
- Permit Issued
- Issued on 7/27/2021
- Issuing Office
- Current Status
- CofO Issued on 10/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2021 | PARISA ZAHABI |
| Corrections Issued | 3/6/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 5/12/2021 | PARISA ZAHABI |
| Plan Check Approved | 5/27/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 5/27/2021 | APPLICANT |
| Issued | 7/27/2021 | APPLICANT |
| CofO in Progress | 10/5/2022 | RICHARD STEINBACH |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
| CofO Issued | 10/6/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2021 | DENNIS BRAGIN |
| Specific Plan | Cleared | 4/6/2021 | KEVIN ARUCAN |
| Hydrant and Access approval | Cleared | 4/25/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: S6000 | 15233 VENTURA BLVD 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Shower Pan | 10/22/2021 | Not Ready for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 4/5/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/12/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/12/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/12/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 9/8/2022 | No Access for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 9/8/2022 | No Access for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/8/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/8/2022 | No Access for Inspection | OGANES TARAKHCHYAN |
| Final | 9/16/2022 | Conditional Approval | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 9/16/2022 | Approved | JOHN KIDWELL |