19341 W FRIAR ST 91335

Certificate Information: 19341 W FRIAR ST 91335

Application / Permit
21016-20000-03307
Plan Check / Job No.
B21VN01535
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20'-2" X 20'-2" (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP AND ENGINEERING DETAIL.
Permit Issued
Issued on 9/15/2021
Issuing Office
Current Status
CofO Issued on 2/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/19/2021 RAPHAEL ROSAS
Corrections Issued 2/20/2021 RAPHAEL ROSAS
Applicant returned to address corrections 7/2/2021 RAPHAEL ROSAS
Plan Check Approved 7/25/2021 RAPHAEL ROSAS
Building Plans Picked Up 8/10/2021 APPLICANT
Issued 9/15/2021 APPLICANT
CofO in Progress 2/17/2022 STEVEN BACK
Permit Finaled 2/18/2022 JOHN JANSON
CofO Issued 2/18/2022 JOHN JANSON
Permit Finaled 2/18/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/9/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/9/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/9/2021 JOHN TRIANTAFYLLOS
ZI Cleared 3/9/2021 LAUREN PADICK
Construction near power lines Cleared 6/12/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/29/2021 Partial Approval HENRY KIM
Pre-Inspection 9/29/2021 Partial Inspection KRISTEN CAUSEY
Sewer 9/29/2021 Approved HENRY KIM
Underground Mechanical 9/29/2021 Corrections Issued HENRY KIM
Deputy Drilled-In Anchors 10/5/2021 Approved JESUS PINEDA
Footing/Foundation/Slab 10/5/2021 Corrections Issued HENRY KIM
Underground Mechanical 10/5/2021 Corrections Issued HENRY KIM
Deputy Drilled-In Anchors 10/6/2021 Conditional Approval HENRY KIM
Footing/Foundation/Slab 10/8/2021 Approved HENRY KIM
BUILDING-Rough-Frame 10/28/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 10/28/2021 Corrections Issued HENRY KIM
HVAC-Rough 10/28/2021 Partial Approval HENRY KIM
PLUMBING-Rough 10/28/2021 Corrections Issued HENRY KIM
Underground Mechanical 10/28/2021 Approved HENRY KIM
BUILDING-Rough-Frame 11/5/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 11/5/2021 Approved STEVEN BACK
HVAC-Rough 11/5/2021 Approved STEVEN BACK
PLUMBING-Rough 11/5/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 11/12/2021 Partial Approval STEVEN BACK
Insulation 11/12/2021 Approved STEVEN BACK
Interior/Exterior Lathing 11/12/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 11/19/2021 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/19/2021 Approved STEVEN BACK
Green Building Rough 11/19/2021 Approved STEVEN BACK
Drywall Nailing 12/1/2021 Approved STEVEN BACK
Final 1/20/2022 Corrections Issued STEVEN BACK
Green Building Final 1/20/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 1/20/2022 SGSOV Approved STEVEN BACK
Smoke Detectors 1/20/2022 Not Ready for Inspection STEVEN BACK
Final 2/2/2022 Corrections Issued STEVEN BACK
Smoke Detectors 2/2/2022 Not Ready for Inspection STEVEN BACK
Final 2/10/2022 Corrections Issued STEVEN BACK
Smoke Detectors 2/10/2022 Not Ready for Inspection STEVEN BACK
Final 2/17/2022 OK to Issue CofO STEVEN BACK
Smoke Detectors 2/17/2022 Approved STEVEN BACK