14656-14658 W HAYNES ST 91411

Certificate Information: 14656-14658 W HAYNES ST 91411

Application / Permit
21016-20000-03297
Plan Check / Job No.
B21VN01529
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 18'-2" X 18'-3" ATTACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A). ALL WORK PER WFPP.
Permit Issued
Issued on 5/25/2021
Issuing Office
Current Status
CofO Issued on 3/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2021 APPLICANT
Assigned to Plan Check Engineer 2/19/2021 JENNIFER LEE
Corrections Issued 2/23/2021 JENNIFER LEE
Applicant returned to address corrections 4/22/2021 JENNIFER LEE
Applicant returned to address corrections 5/10/2021 JENNIFER LEE
Plan Check Approved 5/24/2021 JENNIFER LEE
Issued 5/25/2021 APPLICANT
Building Plans Picked Up 5/25/2021 APPLICANT
CofO in Progress 9/24/2021 RICHARD DOCKUS
Permit Finaled 3/20/2023 DANIEL ORRANTE
CofO Issued 3/20/2023 DANIEL ORRANTE
Permit Finaled 3/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/1/2021 MARKOS PEREZ-BRAN
CPC Cleared 3/1/2021 LAUREN PADICK
CPC Cleared 3/1/2021 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 3/1/2021 MARKOS PEREZ-BRAN
Permit Cleared 3/1/2021 MARKOS PEREZ-BRAN
Sewer availability Cleared 3/1/2021 MARKOS PEREZ-BRAN
ZA Case Cleared 3/1/2021 LAUREN PADICK
HPOZ Cleared 5/3/2021 SUKI GERSHENHORN
ZI Cleared 5/3/2021 SUKI GERSHENHORN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/7/2021 Corrections Issued ARTHUR SARGSYAN
Footing/Foundation/Slab 7/13/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 7/13/2021 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 7/21/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 7/21/2021 Approved ARTHUR SARGSYAN
Green Building Rough 7/21/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 7/21/2021 Approved ARTHUR SARGSYAN
Insulation 7/28/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 7/28/2021 Approved ALAN MORELOS
Shower Pan 7/28/2021 Approved ALAN MORELOS
Drywall Nailing 8/3/2021 Approved ALAN MORELOS
ELECTRICAL-Final 9/10/2021 Corrections Issued RICHARD DOCKUS
Final 9/10/2021 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 9/10/2021 Approved RICHARD DOCKUS
HVAC-Final 9/10/2021 Approved RICHARD DOCKUS
PLUMBING-Final 9/10/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 9/10/2021 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 9/10/2021 Approved RICHARD DOCKUS
Final 9/23/2021 OK to Issue CofO RICHARD DOCKUS