5160 N YOLANDA AVE 91356
Certificate Information: 5160 N YOLANDA AVE 91356
- Application / Permit
- 21016-20000-03059
- Plan Check / Job No.
- B21VN01410
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND ALTERATIONS TO CREATE A NEW BEDROOM, POWDER ROOM, RELOCATE THE MASTER BATHROOM, AND WALK IN CLOSET. CREATE A LAUNDRY ROOM, REMODEL THE KITCHEN, AND REMOVE AND REPLACE WINDOWS AND ADD FOUR NEW WINDOWS. ALL WORK PER ENGINEERING. *** FIRE SPRINKLER NFPA-13D SHALL BE INSTALLED THRU-OUT THE BUILDING ***
- Permit Issued
- Issued on 4/8/2021
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 6/24/2022
Permit Application Status History
| Submitted | 2/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2021 | PARISA ZAHABI |
| Corrections Issued | 2/17/2021 | PARISA ZAHABI |
| Plan Check Approved | 3/22/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 3/25/2021 | APPLICANT |
| Issued | 4/8/2021 | APPLICANT |
| Permit Finaled | 6/23/2022 | DAVID SANDOVAL |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/11/2021 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/16/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/18/2021 | Corrections Issued | RONALD COWAN |
| BUILDING-Rough-Frame | 7/12/2021 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2021 | Approved | RYAN SALAZAR |
| Shower Pan | 9/1/2021 | Partial Approval | DAVID SANDOVAL |
| ELECTRICAL-Rough | 9/3/2021 | Corrections Issued | DAVID SANDOVAL |
| HVAC-Rough | 9/3/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Interior/Exterior Lathing | 9/3/2021 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 9/3/2021 | Approved | DAVID SANDOVAL |
| Shower Pan | 9/3/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 9/16/2021 | Approved | DAVID SANDOVAL |
| Insulation | 9/16/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 9/16/2021 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 9/29/2021 | Approved | DAVID SANDOVAL |
| Final | 4/6/2022 | Corrections Issued | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 4/6/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| Smoke Detectors | 4/6/2022 | Approved | DAVID SANDOVAL |
| Final | 5/11/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Approved | DAVID SANDOVAL |
| Final | 6/23/2022 | Permit Finaled | DAVID SANDOVAL |