5160 N YOLANDA AVE 91356

Certificate Information: 5160 N YOLANDA AVE 91356

Application / Permit
21016-20000-03059
Plan Check / Job No.
B21VN01410
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND ALTERATIONS TO CREATE A NEW BEDROOM, POWDER ROOM, RELOCATE THE MASTER BATHROOM, AND WALK IN CLOSET. CREATE A LAUNDRY ROOM, REMODEL THE KITCHEN, AND REMOVE AND REPLACE WINDOWS AND ADD FOUR NEW WINDOWS. ALL WORK PER ENGINEERING. *** FIRE SPRINKLER NFPA-13D SHALL BE INSTALLED THRU-OUT THE BUILDING ***
Permit Issued
Issued on 4/8/2021
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 6/24/2022

Permit Application Status History

Submitted 2/4/2021 APPLICANT
Assigned to Plan Check Engineer 2/17/2021 PARISA ZAHABI
Corrections Issued 2/17/2021 PARISA ZAHABI
Plan Check Approved 3/22/2021 PARISA ZAHABI
Building Plans Picked Up 3/25/2021 APPLICANT
Issued 4/8/2021 APPLICANT
Permit Finaled 6/23/2022 DAVID SANDOVAL

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/11/2021 BRIAN MILLER
Eng Process Fee Ord 176,300 Cleared 3/16/2021 ADRIAN CASTRO
Sewer availability Cleared 3/16/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/18/2021 Corrections Issued RONALD COWAN
BUILDING-Rough-Frame 7/12/2021 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/12/2021 Approved RYAN SALAZAR
Shower Pan 9/1/2021 Partial Approval DAVID SANDOVAL
ELECTRICAL-Rough 9/3/2021 Corrections Issued DAVID SANDOVAL
HVAC-Rough 9/3/2021 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 9/3/2021 Partial Approval DAVID SANDOVAL
PLUMBING-Rough 9/3/2021 Approved DAVID SANDOVAL
Shower Pan 9/3/2021 Not Ready for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 9/16/2021 Approved DAVID SANDOVAL
Insulation 9/16/2021 Approved DAVID SANDOVAL
Interior/Exterior Lathing 9/16/2021 Approved DAVID SANDOVAL
Drywall Nailing 9/29/2021 Approved DAVID SANDOVAL
Final 4/6/2022 Corrections Issued DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 4/6/2022 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 4/6/2022 Approved DAVID SANDOVAL
Final 5/11/2022 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Approved DAVID SANDOVAL
Final 6/23/2022 Permit Finaled DAVID SANDOVAL