6724-6726 N BELMAR AVE 91335
Certificate Information: 6724-6726 N BELMAR AVE 91335
- Application / Permit
- 21016-20000-03044
- Plan Check / Job No.
- B21VN01404
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (360 SQ FT) PER LAMC 12.22 A. 33(c) and (e)
- Permit Issued
- Issued on 6/7/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 2/20/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 4/28/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/30/2021 | APPLICANT |
| Issued | 6/7/2021 | APPLICANT |
| CofO in Progress | 9/17/2021 | VINCENT HANLEY |
| Permit Finaled | 9/17/2021 | JOHN JANSON |
| CofO Issued | 9/17/2021 | JOHN JANSON |
| Permit Finaled | 9/17/2021 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 3/4/2021 | LAUREN PADICK |
| Address approval | Cleared | 3/16/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/16/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/22/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/7/2021 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/8/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/15/2021 | Partial Approval | VINCENT HANLEY |
| Sewer | 7/15/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/26/2021 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 7/26/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 7/26/2021 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 7/26/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/27/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 7/27/2021 | Approved | VINCENT HANLEY |
| Insulation | 7/27/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/27/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 7/30/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/15/2021 | Approved | VINCENT HANLEY |
| Final | 9/15/2021 | Partial Approval | VINCENT HANLEY |
| Gas Test | 9/15/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 9/15/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 9/15/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 9/15/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 9/15/2021 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 9/15/2021 | Approved | VINCENT HANLEY |
| Smoke Detectors | 9/15/2021 | Approved | VINCENT HANLEY |
| Final | 9/17/2021 | OK to Issue CofO | VINCENT HANLEY |