644 S RIMPAU BLVD 90005

Certificate Information: 644 S RIMPAU BLVD 90005

Application / Permit
21016-20000-03040
Plan Check / Job No.
B21VN01401
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL (N) INT PARTITION WALL BET KITCHEN / PANTRY @ 1ST FLR & INTERIOR PARTITION WALL BET MASTER BATH/ WALKING CLOSET @ 2ND FLR TO (E) 2- STORY SINGLE FAMILY DWELLING WITH ATT GARAGE AND FOUNDATION REPAIR. WORK PER ENGINEER.
Permit Issued
Issued on 7/30/2021
Issuing Office
Current Status
Issued on 7/30/2021

Permit Application Status History

Submitted 2/4/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 TROY DEGUZMAN
Corrections Issued 2/14/2021 TROY DEGUZMAN
Quality Review Completed 2/16/2021 CHON CHIO KUO
Applicant returned to address corrections 6/24/2021 TROY DEGUZMAN
Applicant returned to address corrections 7/21/2021 TROY DEGUZMAN
Applicant returned to address corrections 7/28/2021 TROY DEGUZMAN
Plan Check Approved 7/28/2021 TROY DEGUZMAN
Issued 7/30/2021 APPLICANT

Permit Application Clearance Information

CPC Cleared 5/18/2021 SUKI GERSHENHORN
HPOZ Cleared 5/18/2021 SUKI GERSHENHORN
Miscellaneous Cleared 5/18/2021 SUKI GERSHENHORN
Miscellaneous Cleared 5/18/2021 SUKI GERSHENHORN
ZA Case Cleared 5/18/2021 SUKI GERSHENHORN
ZA Case Cleared 5/18/2021 SUKI GERSHENHORN
ZI Cleared 5/18/2021 SUKI GERSHENHORN
Specific Plan Cleared 5/19/2021 MIGUEL GAMBOA
ZI Cleared 5/19/2021 MIGUEL GAMBOA
Green Code Cleared 5/27/2021 TROY DEGUZMAN
Sewer availability Cleared 6/1/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/2/2021 STEVE MELGAR

Contact Information

Contractor D C Keeton Home Improvements; Lic. No.: 715043-B 616 ST PAUL AVE #535      LOS ANGELES, CA 90017
Engineer Li,, Dacheng David; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/12/2021 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Rough 8/12/2021 Partial Approval ARTHUR SARGSYAN
Footing/Foundation/Slab 8/12/2021 Approved ARTHUR SARGSYAN
METHANE-Rough 8/12/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 8/12/2021 Partial Approval ARTHUR SARGSYAN
Drywall Nailing 8/18/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 8/20/2021 Approved ARTHUR SARGSYAN
Pre-Inspection 12/15/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 12/28/2022 Not Ready for Inspection MICHAEL LEWIS
Wood Frame 12/28/2022 Partial Approval MICHAEL LEWIS
Footing/Foundation/Slab 1/4/2023 Approved RICHARD DOCKUS
Insulation 1/4/2023 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 1/4/2023 Not Ready for Inspection RICHARD DOCKUS
Drywall Nailing 1/5/2023 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 1/24/2023 Approved RICHARD DOCKUS
PLUMBING-Rough 1/24/2023 Approved RICHARD DOCKUS
Wood Frame 1/24/2023 Approved RICHARD DOCKUS
ELECTRICAL-Rough 2/24/2023 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/24/2023 Partial Approval ALIZAH MAYAGOITIA
Light Gage Steel Frame 2/24/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Shower Pan 3/3/2023 Approved RICHARD DOCKUS
Interior/Exterior Lathing 3/13/2023 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 5/18/2023 Not Ready for Inspection RICHARD DOCKUS
HVAC-Rough 5/18/2023 Approved RICHARD DOCKUS
ELECTRICAL-Rough 5/24/2023 Approved RICHARD DOCKUS
Structural Steel Frame 5/24/2023 Approved RICHARD DOCKUS
Insulation 6/2/2023 Corrections Issued RICHARD DOCKUS
Drywall Nailing 6/13/2023 Approved RICHARD DOCKUS